South Fambridge Hall - Solar farm & Battery storage
South Fambridge Hall - Solar farm & Battery storage is a 20 MW battery storage site under construction in Rochford. Planning permission was granted on 15 December 2021, 6 months after submission. Operator of record: British Solar Renewables / BayWa r.e. UK Limited.
Planning and build timeline
| Application submitted | 22 June 2021 |
| Permission granted | 15 December 2021 6 months after submission |
| Operational | not recorded |
Screening a site of your own?
Redline runs the record on your own boundary in Rochford: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with South Fambridge Hall - Solar farm & Battery storage’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
- Green Belt — Rochford
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Solar Photovoltaics · Under Construction | 49.99 | 0 km |
Solar Photovoltaics · Operational | 5 | 1 km |
Solar Photovoltaics · Operational | 2.5 | 5.8 km |
Solar Photovoltaics · Under Construction | 30 | 8.1 km |
Solar Photovoltaics · Operational | 25 | 8.8 km |
Landfill Gas · Operational | 2.4 | 8.9 km |
Battery · Operational | 99.98 | 9.4 km |
Solar Photovoltaics · Operational | 5 | 10.7 km |
How big is South Fambridge Hall - Solar farm & Battery storage?
South Fambridge Hall - Solar farm & Battery storage has a recorded installed capacity of 20 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates South Fambridge Hall - Solar farm & Battery storage?
REPD records the operator as British Solar Renewables / BayWa r.e. UK Limited. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was South Fambridge Hall - Solar farm & Battery storage approved and built?
The application was submitted on 22 June 2021. Permission was granted on 15 December 2021, 6 months later. The site is recorded as under construction and has no operational date yet.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 9274.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode