Kype Muir Wind Farm Extension
Kype Muir Wind Farm Extension is operational in Scotland with a recorded capacity of 67.2 MW, and has been generating since 2024-10-01.
Planning and build timeline
| Application submitted | 2014-10-10 |
| Permission granted | 2016-09-16 23 months after submission |
| Operational | 2024-10-01 96 months after consent |
Scottish Government (S36)’s record on onshore wind
Scottish Government (S36) has decided 173 onshore wind schemes and approved 80%, taking a median of 33.7 months. See every onshore wind scheme decision in Scottish Government (S36) →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Kype Muir Wind Farm Wind Onshore · Operational | 88.4 | 0 km |
Auchrobert Wind Farm Wind Onshore · Operational | 36 | 3.4 km |
Dungavel Hill Wind Onshore · Operational | 29.9 | 4.7 km |
Strathaven Airfield Solar Photovoltaics · Operational | — | 6.9 km |
LADEHEAD FARM - WIND TURBINES Wind Onshore · Operational | 2.4 | 7.4 km |
Lochhead Farm Wind Onshore · Operational | 6 | 7.8 km |
Woodlands Wind Farm Wind Onshore · Operational | 2.6 | 7.9 km |
Nutberry Wind Farm Wind Onshore · Operational | 15 | 8.1 km |
How big is Kype Muir Wind Farm Extension?
Kype Muir Wind Farm Extension has a recorded installed capacity of 67.2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Kype Muir Wind Farm Extension?
REPD records the operator as Banks Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Kype Muir Wind Farm Extension approved and built?
The application was submitted on 2014-10-10. Permission was granted on 2016-09-16, 23 months later. The site became operational on 2024-10-01, 96 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4628.