Kype Muir Wind Farm
Kype Muir Wind Farm is an operational 88.4 MW onshore wind farm in Scotland, generating since 15 September 2019. Planning permission was granted on 22 May 2014, 33 months after submission. Operator of record: Banks Renewables.
Planning and build timeline
| Application submitted | 9 August 2011 |
| Permission granted | 22 May 2014 33 months after submission |
| Operational | 15 September 2019 64 months after consent |
Screening a site of your own?
Redline runs the same record on your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Kype Muir Wind Farm’s recorded coordinate — swap in your own postcode or coordinates.
Scottish Government (S36)’s record on onshore wind
Scottish Government (S36) has decided 173 onshore wind schemes and approved 80%, taking a median of 33.7 months. See every onshore wind scheme decision in Scottish Government (S36) →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 67.2 | 0 km |
Wind Onshore · Operational | 36 | 3.4 km |
Wind Onshore · Operational | 29.9 | 4.7 km |
Solar Photovoltaics · Operational | — | 6.9 km |
Wind Onshore · Operational | 2.4 | 7.4 km |
Wind Onshore · Operational | 6 | 7.8 km |
Wind Onshore · Operational | 2.6 | 7.9 km |
Wind Onshore · Operational | 15 | 8.1 km |
How big is Kype Muir Wind Farm?
Kype Muir Wind Farm has a recorded installed capacity of 88.4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Kype Muir Wind Farm?
REPD records the operator as Banks Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Kype Muir Wind Farm approved and built?
The application was submitted on 9 August 2011. Permission was granted on 22 May 2014, 33 months later. The site became operational on 15 September 2019, 64 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4643.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode