Henry Colbeck Office is an operational 0.2 MW solar farm in North Lanarkshire, generating since 1 March 2019. Planning permission was granted on 23 May 2019, 2 months after submission. Operator of record: Henry Colbeck.
Planning and build timeline
| Application submitted | 1 April 2019 |
| Permission granted | 23 May 2019 2 months after submission |
| Operational | 1 March 2019 |
Screening a site of your own?
North Lanarkshire approves 100% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Henry Colbeck Office’s recorded coordinate — swap in your own postcode or coordinates.
North Lanarkshire’s record on solar
North Lanarkshire has decided 14 solar farms and approved 100%, taking a median of 1.1 months. See every solar farm decision in North Lanarkshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Advanced Conversion Technologies · Under Construction | 25 | 1.5 km |
Wind Onshore · Operational | 2.5 | 5 km |
Landfill Gas · Operational | 1.9 | 6.3 km |
Small Hydro · Operational | — | 7 km |
Landfill Gas · Operational | 2 | 7.2 km |
Landfill Gas · Operational | 2 | 7.2 km |
Landfill Gas · Operational | 2.2 | 7.2 km |
Landfill Gas · Operational | 1.9 | 7.2 km |
How big is Henry Colbeck Office?
Henry Colbeck Office has a recorded installed capacity of 0.2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Henry Colbeck Office?
REPD records the operator as Henry Colbeck. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Henry Colbeck Office approved and built?
The application was submitted on 1 April 2019. Permission was granted on 23 May 2019, 2 months later. The site became operational on 1 March 2019.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 7391.