Renewable sitesDamhead Farm

Damhead Farm

Damhead Farm is an operational 2.5 MW onshore wind farm in North Lanarkshire, generating since 17 May 2013. Planning permission was granted on 14 January 2010, 32 months after submission. Operator of record: Private Developer.

2.5 MW
Capacity
as recorded in REPD
Operational
Status
since 17 May 2013
Wind Onshore
Technology
Private Developer
North Lanarkshire
Authority
Scotland

Planning and build timeline

Application submitted11 May 2007
Permission granted14 January 2010
32 months after submission
Operational17 May 2013
40 months after consent

Screening a site of your own?

RedlineUK · £39

North Lanarkshire approves 70% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Damhead Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

North Lanarkshire’s record on onshore wind

North Lanarkshire has decided 20 onshore wind schemes and approved 70%, taking a median of 16.8 months. See every onshore wind scheme decision in North Lanarkshire

Other built sites within 15 km

SiteMWDistance
Landfill Gas · Operational
1.94.3 km
Advanced Conversion Technologies · Under Construction
254.9 km
Solar Photovoltaics · Operational
0.25 km
Landfill Gas · Operational
2.35.4 km
Wind Onshore · Operational
245.4 km
Landfill Gas · Operational
25.7 km
Landfill Gas · Operational
25.7 km
Landfill Gas · Operational
2.25.7 km

How big is Damhead Farm?

Damhead Farm has a recorded installed capacity of 2.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Damhead Farm?

REPD records the operator as Private Developer. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Damhead Farm approved and built?

The application was submitted on 11 May 2007. Permission was granted on 14 January 2010, 32 months later. The site became operational on 17 May 2013, 40 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3747.