Renewable sitesDamhead Farm

Damhead Farm

Damhead Farm is operational in North Lanarkshire with a recorded capacity of 2.5 MW, and has been generating since 2013-05-17.

2.5 MW
Capacity
as recorded in REPD
Operational
Status
since 2013-05-17
Wind Onshore
Technology
Private Developer
North Lanarkshire
Authority
Scotland

Planning and build timeline

Application submitted2007-05-11
Permission granted2010-01-14
32 months after submission
Operational2013-05-17
40 months after consent

North Lanarkshire’s record on onshore wind

North Lanarkshire has decided 20 onshore wind schemes and approved 70%, taking a median of 16.8 months. See every onshore wind scheme decision in North Lanarkshire

Other built sites within 15 km

SiteMWDistance
Greengairs Landfill Scheme Phase I
Landfill Gas · Operational
1.94.3 km
Coatbridge Material Recovery and Renewable Energy Facility
Advanced Conversion Technologies · Under Construction
254.9 km
Henry Colbeck Office
Solar Photovoltaics · Operational
0.25 km
Auchinlea Landfill Site
Landfill Gas · Operational
2.35.4 km
Greengairs East Wind Farm
Wind Onshore · Operational
245.4 km
Greengairs Landfill Scheme Phase III
Landfill Gas · Operational
25.7 km
Greengairs Landfill Scheme Phase II
Landfill Gas · Operational
1.95.7 km
Greengairs Landfill Scheme Phase VI
Landfill Gas · Operational
2.25.7 km

How big is Damhead Farm?

Damhead Farm has a recorded installed capacity of 2.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Damhead Farm?

REPD records the operator as Private Developer. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Damhead Farm approved and built?

The application was submitted on 2007-05-11. Permission was granted on 2010-01-14, 32 months later. The site became operational on 2013-05-17, 40 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3747.