Renewable sites › Lapwing Fen 2 - Battery Storage Plant
Lapwing Fen 2 - Battery Storage Plant
Lapwing Fen 2 - Battery Storage Plant is a 250 MW battery storage site under construction in King's Lynn and West Norfolk. Planning permission was granted on 27 April 2020, 5 months after submission. Operator of record: Tribus Clean Energy.
Planning and build timeline
| Application submitted | 25 November 2019 |
| Permission granted | 27 April 2020 5 months after submission |
| Operational | not recorded |
Screening a site of your own?
King's Lynn and West Norfolk approves 100% of battery storage schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Lapwing Fen 2 - Battery Storage Plant’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 1 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
King's Lynn and West Norfolk’s record on battery storage
King's Lynn and West Norfolk has decided 15 battery storage schemes and approved 100%, taking a median of 6.7 months. See every battery storage scheme decision in King's Lynn and West Norfolk →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Solar Photovoltaics · Under Construction | 40 | 2 km |
Solar Photovoltaics · Operational | 30 | 2.5 km |
Wind Onshore · Operational | 14 | 2.5 km |
Solar Photovoltaics · Operational | 49.9 | 3.5 km |
Solar Photovoltaics · Operational | 1.7 | 7.3 km |
Solar Photovoltaics · Operational | 1 | 7.3 km |
Solar Photovoltaics · Operational | 12.7 | 8.4 km |
Solar Photovoltaics · Operational | 0.2 | 9.1 km |
How big is Lapwing Fen 2 - Battery Storage Plant?
Lapwing Fen 2 - Battery Storage Plant has a recorded installed capacity of 250 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Lapwing Fen 2 - Battery Storage Plant?
REPD records the operator as Tribus Clean Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Lapwing Fen 2 - Battery Storage Plant approved and built?
The application was submitted on 25 November 2019. Permission was granted on 27 April 2020, 5 months later. The site is recorded as under construction and has no operational date yet.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 7614.