Novarly ParcelRenewable sites

Renewable sitesSutton Bridge Solar Farm

Sutton Bridge Solar Farm

Sutton Bridge Solar Farm is an operational 49.9 MW solar farm in South Holland, generating since 1 April 2024. Planning permission was granted on 26 January 2021, 2 months after submission. Operator of record: EDF Energy Renewables.

49.9 MW
Capacity
as recorded in REPD
Operational
Status
since 1 April 2024
Solar Photovoltaics
Technology
EDF Energy Renewables
South Holland
Authority
England

Planning and build timeline

Application submitted11 December 2020
Permission granted26 January 2021
2 months after submission
Operational1 April 2024
38 months after consent

Screening a site of your own?

RedlineUK · £39

South Holland approves 88% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Sutton Bridge Solar Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 1 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

South Holland’s record on solar

South Holland has decided 24 solar farms and approved 88%, taking a median of 2.5 months. See every solar farm decision in South Holland

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
142 km
Battery · Under Construction
2503.5 km
Solar Photovoltaics · Under Construction
403.9 km
Solar Photovoltaics · Operational
305 km
Solar Photovoltaics · Operational
15.3 km
Solar Photovoltaics · Operational
1.75.4 km
Solar Photovoltaics · Operational
12.79.7 km
Wind Onshore · Operational
1210.5 km

How big is Sutton Bridge Solar Farm?

Sutton Bridge Solar Farm has a recorded installed capacity of 49.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Sutton Bridge Solar Farm?

REPD records the operator as EDF Energy Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Sutton Bridge Solar Farm approved and built?

The application was submitted on 11 December 2020. Permission was granted on 26 January 2021, 2 months later. The site became operational on 1 April 2024, 38 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 16008.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode