Walpole Bank is under construction in King's Lynn and West Norfolk with a recorded capacity of 40 MW.

40 MW
Capacity
as recorded in REPD
Under Construction
Status
no operational date
Solar Photovoltaics
Technology
DIF Capital Partners / Green Investment Group
King's Lynn and West Norfolk
Authority
England

Planning and build timeline

Application submitted2020-09-25
Permission granted2021-01-15
4 months after submission
Operationalnot recorded

What this site sits on

The recorded coordinate falls on land surveyed as Grade 1 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

King's Lynn and West Norfolk’s record on solar

King's Lynn and West Norfolk has decided 31 solar farms and approved 97%, taking a median of 2.9 months. See every solar farm decision in King's Lynn and West Norfolk

Other built sites within 15 km

SiteMWDistance
Rose And Crown Farm
Solar Photovoltaics · Operational
301.2 km
Lapwing Fen 2 - Battery Storage Plant
Battery · Under Construction
2502 km
The Grange Wind Farm
Wind Onshore · Operational
143.8 km
Sutton Bridge Solar Farm
Solar Photovoltaics · Operational
49.93.9 km
Long Sutton Butterfly And Wildlife Park (extension)
Solar Photovoltaics · Operational
18.7 km
Long Sutton Butterfly And Wildlife Park
Solar Photovoltaics · Operational
1.78.7 km
Wisbech Solar Farm
Solar Photovoltaics · Operational
3.59.8 km
Volmary Site
Solar Photovoltaics · Operational
0.29.8 km

How big is Walpole Bank?

Walpole Bank has a recorded installed capacity of 40 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Walpole Bank?

REPD records the operator as DIF Capital Partners / Green Investment Group. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Walpole Bank approved and built?

The application was submitted on 2020-09-25. Permission was granted on 2021-01-15, 4 months later. The site is recorded as under construction and has no operational date yet.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 9524.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council