Novarly ParcelRenewable sites

Renewable sitesThe Grange Wind Farm

The Grange Wind Farm

The Grange Wind Farm is an operational 14 MW onshore wind farm in South Holland, generating since 1 March 2013. Planning permission was granted on 15 October 2010, 16 months after submission. Operator of record: Renewable Energy Systems (RES).

14 MW
Capacity
as recorded in REPD
Operational
Status
since 1 March 2013
Wind Onshore
Technology
Renewable Energy Systems (RES)
South Holland
Authority
England

Planning and build timeline

Application submitted17 June 2009
Permission granted15 October 2010
16 months after submission
Operational1 March 2013
29 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in South Holland: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with The Grange Wind Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 1 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
49.92 km
Battery · Under Construction
2502.5 km
Solar Photovoltaics · Under Construction
403.8 km
Solar Photovoltaics · Operational
304.8 km
Solar Photovoltaics · Operational
1.74.9 km
Solar Photovoltaics · Operational
14.9 km
Solar Photovoltaics · Operational
12.77.8 km
Wind Onshore · Operational
1210.3 km

How big is The Grange Wind Farm?

The Grange Wind Farm has a recorded installed capacity of 14 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates The Grange Wind Farm?

REPD records the operator as Renewable Energy Systems (RES). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was The Grange Wind Farm approved and built?

The application was submitted on 17 June 2009. Permission was granted on 15 October 2010, 16 months later. The site became operational on 1 March 2013, 29 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3671.