Novarly ParcelRenewable sites

Renewable sitesThe Grange Wind Farm

The Grange Wind Farm

The Grange Wind Farm is operational in South Holland with a recorded capacity of 14 MW, and has been generating since 2013-03-01.

14 MW
Capacity
as recorded in REPD
Operational
Status
since 2013-03-01
Wind Onshore
Technology
Renewable Energy Systems (RES)
South Holland
Authority
England

Planning and build timeline

Application submitted2009-06-17
Permission granted2010-10-15
16 months after submission
Operational2013-03-01
29 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 1 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Sutton Bridge Solar Farm
Solar Photovoltaics · Operational
49.92 km
Lapwing Fen 2 - Battery Storage Plant
Battery · Under Construction
2502.5 km
Walpole Bank
Solar Photovoltaics · Under Construction
403.8 km
Rose And Crown Farm
Solar Photovoltaics · Operational
304.8 km
Long Sutton Butterfly And Wildlife Park
Solar Photovoltaics · Operational
1.74.9 km
Long Sutton Butterfly And Wildlife Park (extension)
Solar Photovoltaics · Operational
14.9 km
Grange Farm (Lincolnshire)
Solar Photovoltaics · Operational
12.77.8 km
Gedney Marsh
Wind Onshore · Operational
1210.3 km

How big is The Grange Wind Farm?

The Grange Wind Farm has a recorded installed capacity of 14 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates The Grange Wind Farm?

REPD records the operator as Renewable Energy Systems (RES). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was The Grange Wind Farm approved and built?

The application was submitted on 2009-06-17. Permission was granted on 2010-10-15, 16 months later. The site became operational on 2013-03-01, 29 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3671.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council