Renewable sites › Rose And Crown Farm
Rose And Crown Farm
Rose And Crown Farm is operational in King's Lynn and West Norfolk with a recorded capacity of 30 MW, and has been generating since 2016-03-18.
Planning and build timeline
| Application submitted | 2014-02-25 |
| Permission granted | 2015-09-11 18 months after submission |
| Operational | 2016-03-18 6 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 2 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
King's Lynn and West Norfolk’s record on solar
King's Lynn and West Norfolk has decided 31 solar farms and approved 97%, taking a median of 2.9 months. See every solar farm decision in King's Lynn and West Norfolk →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Walpole Bank Solar Photovoltaics · Under Construction | 40 | 1.2 km |
Lapwing Fen 2 - Battery Storage Plant Battery · Under Construction | 250 | 2.5 km |
The Grange Wind Farm Wind Onshore · Operational | 14 | 4.8 km |
Sutton Bridge Solar Farm Solar Photovoltaics · Operational | 49.9 | 5 km |
Wisbech Solar Farm Solar Photovoltaics · Operational | 3.5 | 8.6 km |
Volmary Site Solar Photovoltaics · Operational | 0.2 | 8.8 km |
Long Sutton Butterfly And Wildlife Park Solar Photovoltaics · Operational | 1.7 | 9.6 km |
Long Sutton Butterfly And Wildlife Park (extension) Solar Photovoltaics · Operational | 1 | 9.6 km |
How big is Rose And Crown Farm?
Rose And Crown Farm has a recorded installed capacity of 30 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Rose And Crown Farm?
REPD records the operator as Elgin Energy EsCo. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Rose And Crown Farm approved and built?
The application was submitted on 2014-02-25. Permission was granted on 2015-09-11, 18 months later. The site became operational on 2016-03-18, 6 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1783.