Renewable sitesGrange Farm (Lincolnshire)

Grange Farm (Lincolnshire)

Grange Farm (Lincolnshire) is an operational 12.7 MW solar farm in South Holland, generating since 30 March 2015. Planning permission was granted on 19 March 2014, 5 months after submission. Operator of record: Green Switch Solutions.

12.7 MW
Capacity
as recorded in REPD
Operational
Status
since 30 March 2015
Solar Photovoltaics
Technology
Green Switch Solutions
South Holland
Authority
England

Planning and build timeline

Application submitted1 November 2013
Permission granted19 March 2014
5 months after submission
Operational30 March 2015
12 months after consent

Screening a site of your own?

RedlineUK · £39

South Holland approves 88% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Grange Farm (Lincolnshire)’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 2 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

South Holland’s record on solar

South Holland has decided 24 solar farms and approved 88%, taking a median of 2.5 months. See every solar farm decision in South Holland

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
1.77.5 km
Solar Photovoltaics · Operational
17.6 km
Wind Onshore · Operational
147.8 km
Battery · Under Construction
2508.4 km
Solar Photovoltaics · Operational
49.99.7 km
Solar Photovoltaics · Operational
0.210 km
Anaerobic Digestion · Operational
1.510.2 km
Solar Photovoltaics · Under Construction
4010.4 km

How big is Grange Farm (Lincolnshire)?

Grange Farm (Lincolnshire) has a recorded installed capacity of 12.7 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Grange Farm (Lincolnshire)?

REPD records the operator as Green Switch Solutions. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Grange Farm (Lincolnshire) approved and built?

The application was submitted on 1 November 2013. Permission was granted on 19 March 2014, 5 months later. The site became operational on 30 March 2015, 12 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2366.