Novarly ParcelRenewable planning

Renewable planning SolarMonmouthshire

Solar planning in Monmouthshire

Monmouthshire has decided 10 solar farms and approved 100% of them, taking a median of 4.4 months to decide. Consented capacity: 41 MW.

100%
Approved
10 granted · 0 refused
4.4 mo
Median decision
UK 2.3 mo
41 MW
Consented
across approved schemes
2
Appeals
2 allowed on appeal

How Monmouthshire compares

Against the 298 UK authorities with 5+ solar decisions, Monmouthshire sits in the 77th percentile for approval rate (7 points above the England average) and the 12th percentile for speed.

Decisions by year

35Approved — 1 (2011)111Approved — 1 (2012)112Approved — 1 (2014)114Approved — 2 (2015)215Approved — 2 (2022)222Approved — 1 (2025)125Approved — 1 (2026)126
Approved Refused

Solar decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (13)

SchemeMWStatusDecided
Newhouse Farm Industrial Estate, Unit 1 - Roof Mounted Solar
Micheldever Tyres - Chepstow · DM/2025/01549 · 1.4 mo to decide
0.28Awaiting Construction2026-01-28
Llanarth Court Hospital, Llanarth Road - Solar Panels
Priory Group · DM/2025/00344 · 6.4 mo to decide
Awaiting Construction2025-10-20
Daisy Cottage, Ty-Canol Road - Solar Panels
Private Developer · DM/2022/01163 · 2 mo to decide
1Awaiting Construction2022-10-27
Morrisons, Abergavenny - Roof Mounted Solar Array
WM Morrisons Supermarkets Plc · DM/2021/01893 · 4 mo to decide
0.23Awaiting Construction2022-03-29
Land North West of Magor Service Station
INRG Solar · DC/2015/00573 · 7.1 mo to decide
5Abandoned2015-12-14
Southbrook Solar Farm
Sunventures (Suncredit UK) · DC/2015/00855 · 4.7 mo to decide
5Operational2015-12-03
Magor Brewery
Perpetum Sun · DC/2015/01158 · 1.1 mo to decide
1.7Abandoned2015-10-30
Rhewl Farm
Renesola · DC/2014/00939 · 10.6 mo to decide
6Operational2015-06-25
Oak Grove Farm
Monmouthshire County Council · DC/2015/00247
5.7Operational2015-03-05
Manor Farm (Monmouthshire)
3C Energy/Conergy · DC/2013/00006 · 21.5 mo to decide
10.5Operational2014-10-24
Buckwell Farm Solar Park
Private Developer · DC/2013/00925 · 9.2 mo to decide
8.1Abandoned2014-08-06
Land at Lower House Farm
3C Energy · DC/2012/00666 · 4.1 mo to decide
8.1Operational2012-12-10
Llancayo Solar Farm
m03 Power · DC/2011/00196 · 1.6 mo to decide
3.9Operational2011-06-03

Does Monmouthshire approve solar farms?

Yes — of the 10 solar farms Monmouthshire has decided, 100% were approved (10 granted, 0 refused). The UK-wide rate for solar is 93%.

How long does a solar farm application take in Monmouthshire?

The median time from application to decision is 4.4 months, against a UK median of 2.3 months for solar. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much solar capacity has Monmouthshire consented?

41 MW has been consented across 10 approved schemes. There are no applications currently awaiting a decision.

Other technologies in Monmouthshire

Battery storage in MonmouthshireOnshore wind in Monmouthshire

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.