Novarly ParcelRenewable sites

Renewable sitesManor Farm (Monmouthshire)

Manor Farm (Monmouthshire)

Manor Farm (Monmouthshire) is operational in Monmouthshire with a recorded capacity of 10.5 MW, and has been generating since 2016-06-23.

10.5 MW
Capacity
as recorded in REPD
Operational
Status
since 2016-06-23
Solar Photovoltaics
Technology
3C Energy/Conergy
Monmouthshire
Authority
Wales

Planning and build timeline

Application submitted2013-01-07
Permission granted2014-10-24
22 months after submission
Operational2016-06-23
20 months after consent

Monmouthshire’s record on solar

Monmouthshire has decided 10 solar farms and approved 100%, taking a median of 4.4 months. See every solar farm decision in Monmouthshire

Other built sites within 15 km

SiteMWDistance
Penpergwm Solar Farm (Great House Farm)
Solar Photovoltaics · Under Construction
325.3 km
Clytha Road - Biomass Boiler Unit
Biomass (dedicated) · Operational
0.9911.1 km
Land at Lower House Farm
Solar Photovoltaics · Operational
8.111.3 km
Llancayo Solar Farm
Solar Photovoltaics · Operational
3.912.5 km
Mamhilad Solar Farm
Solar Photovoltaics · Operational
514.4 km

How big is Manor Farm (Monmouthshire)?

Manor Farm (Monmouthshire) has a recorded installed capacity of 10.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Manor Farm (Monmouthshire)?

REPD records the operator as 3C Energy/Conergy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Manor Farm (Monmouthshire) approved and built?

The application was submitted on 2013-01-07. Permission was granted on 2014-10-24, 22 months later. The site became operational on 2016-06-23, 20 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1746.

Novarly Parcel · official public data, read properly · parcel.novarly.com