Cumberhead West Wind Farm is a 126 MW onshore wind farm under construction in Scotland. Planning permission was granted on 18 November 2021, 12 months after submission. Operator of record: 3R Energy Solutions Limited.

126 MW
Capacity
as recorded in REPD
Under Construction
Status
no operational date
Wind Onshore
Technology
3R Energy Solutions Limited
National
Authority
Scotland

Planning and build timeline

Application submitted2 December 2020
Permission granted18 November 2021
12 months after submission
Operationalnot recorded

Screening a site of your own?

RedlineUK · £39

Redline runs the same record on your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Cumberhead West Wind Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Scottish Government (S36)’s record on onshore wind

Scottish Government (S36) has decided 173 onshore wind schemes and approved 80%, taking a median of 33.7 months. See every onshore wind scheme decision in Scottish Government (S36)

Other built sites within 15 km

SiteMWDistance
Battery · Under Construction
400 km
Wind Onshore · Operational
451.3 km
Battery · Under Construction
201.3 km
Wind Onshore · Under Construction
781.3 km
Wind Onshore · Operational
152.2 km
Battery · Under Construction
5002.8 km
Wind Onshore · Operational
2.64.1 km
Wind Onshore · Operational
264.2 km

How big is Cumberhead West Wind Farm?

Cumberhead West Wind Farm has a recorded installed capacity of 126 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Cumberhead West Wind Farm?

REPD records the operator as 3R Energy Solutions Limited. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Cumberhead West Wind Farm approved and built?

The application was submitted on 2 December 2020. Permission was granted on 18 November 2021, 12 months later. The site is recorded as under construction and has no operational date yet.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3328.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode