Nutberry Wind Farm
Nutberry Wind Farm is an operational 15 MW onshore wind farm in South Lanarkshire, generating since 30 September 2013. Planning permission was granted on 5 April 2011, 54 months after submission. Operator of record: Renantis Falck Renewables Limited.
Planning and build timeline
| Application submitted | 28 September 2006 |
| Permission granted | 5 April 2011 54 months after submission |
| Operational | 30 September 2013 30 months after consent |
Screening a site of your own?
South Lanarkshire approves 73% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Nutberry Wind Farm’s recorded coordinate — swap in your own postcode or coordinates.
South Lanarkshire’s record on onshore wind
South Lanarkshire has decided 49 onshore wind schemes and approved 73%, taking a median of 15.9 months. See every onshore wind scheme decision in South Lanarkshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Under Construction | 126 | 2.2 km |
Battery · Under Construction | 40 | 2.2 km |
Battery · Under Construction | 20 | 2.4 km |
Wind Onshore · Under Construction | 78 | 2.4 km |
Wind Onshore · Operational | 45 | 2.4 km |
Wind Onshore · Operational | 26 | 3.7 km |
Wind Onshore · Operational | 2.6 | 3.8 km |
Wind Onshore · Operational | 48 | 3.9 km |
How big is Nutberry Wind Farm?
Nutberry Wind Farm has a recorded installed capacity of 15 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Nutberry Wind Farm?
REPD records the operator as Renantis Falck Renewables Limited. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Nutberry Wind Farm approved and built?
The application was submitted on 28 September 2006. Permission was granted on 5 April 2011, 54 months later. The site became operational on 30 September 2013, 30 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3676.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode