Coalburn Energy - Battery Storage

Coalburn Energy - Battery Storage is a 500 MW battery storage site under construction in Scotland. Planning permission was granted on 7 June 2023, 14 months after submission. Operator of record: Alcemi Storage Development Limited.

500 MW
Capacity
as recorded in REPD
Under Construction
Status
no operational date
Battery
Technology
Alcemi Storage Development Limited
National
Authority
Scotland

Planning and build timeline

Application submitted6 April 2022
Permission granted7 June 2023
14 months after submission
Operationalnot recorded

Screening a site of your own?

RedlineUK · £39

Redline runs the same record on your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Coalburn Energy - Battery Storage’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented battery storage scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Scottish Government (S36)’s record on battery storage

Scottish Government (S36) has decided 108 battery storage schemes and approved 94%, taking a median of 17.3 months. See every battery storage scheme decision in Scottish Government (S36)

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
482.2 km
Battery · Under Construction
402.8 km
Wind Onshore · Under Construction
1262.8 km
Wind Onshore · Operational
453.7 km
Wind Onshore · Under Construction
783.7 km
Battery · Under Construction
203.7 km
Wind Onshore · Operational
2.64.6 km
Wind Onshore · Operational
154.8 km

How big is Coalburn Energy - Battery Storage?

Coalburn Energy - Battery Storage has a recorded installed capacity of 500 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Coalburn Energy - Battery Storage?

REPD records the operator as Alcemi Storage Development Limited. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Coalburn Energy - Battery Storage approved and built?

The application was submitted on 6 April 2022. Permission was granted on 7 June 2023, 14 months later. The site is recorded as under construction and has no operational date yet.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 11034.