Renewable sites › Coalburn Energy - Battery Storage
Coalburn Energy - Battery Storage
Coalburn Energy - Battery Storage is under construction in Scotland with a recorded capacity of 500 MW.
Planning and build timeline
| Application submitted | 2022-04-06 |
| Permission granted | 2023-06-07 14 months after submission |
| Operational | not recorded |
Scottish Government (S36)’s record on battery storage
Scottish Government (S36) has decided 108 battery storage schemes and approved 94%, taking a median of 17.3 months. See every battery storage scheme decision in Scottish Government (S36) →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Broken Cross (Former Surface Mine) Wind Onshore · Operational | 48 | 2.2 km |
Cumberhead West Wind Farm Wind Onshore · Under Construction | 126 | 2.8 km |
Cumberhead West Wind Farm Battery · Under Construction | 40 | 2.8 km |
Douglas West Wind Farm (extension) Battery · Under Construction | 20 | 3.7 km |
Douglas West and Dalquhandy Renewable Energy Project Wind Onshore · Operational | 45 | 3.7 km |
Douglas West Wind Farm (extension) Wind Onshore · Under Construction | 78 | 3.7 km |
Woodlands Wind Farm Wind Onshore · Operational | 2.6 | 4.6 km |
Nutberry Wind Farm Wind Onshore · Operational | 15 | 4.8 km |
How big is Coalburn Energy - Battery Storage?
Coalburn Energy - Battery Storage has a recorded installed capacity of 500 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Coalburn Energy - Battery Storage?
REPD records the operator as Alcemi Storage Development Limited. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Coalburn Energy - Battery Storage approved and built?
The application was submitted on 2022-04-06. Permission was granted on 2023-06-07, 14 months later. The site is recorded as under construction and has no operational date yet.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 11034.