Onshore wind planning in Scottish Government (S36)

Scottish Government (S36) has decided 173 onshore wind schemes and approved 80% of them, taking a median of 33.7 months to decide. Consented capacity: 12,247 MW. 122 applications still awaiting a decision.

80%
Approved
138 granted · 35 refused
33.7 mo
Median decision
UK 11.5 mo
12,247 MW
Consented
3,613 MW refused
43
Appeals
19 allowed on appeal

How Scottish Government (S36) compares

Against the 75 UK authorities with 5+ onshore wind decisions, Scottish Government (S36) sits in the 72nd percentile for approval rate (12 points above the England average) and the 4th percentile for speed.

Decisions by year

1020Approved — 4 (2010)410Approved — 3 (2011)3Approved — 4 (2012)412Approved — 2 (2013)Refused — 3 (2013)5Approved — 10 (2014)Refused — 4 (2014)1414Approved — 4 (2015)Refused — 3 (2015)7Approved — 3 (2016)Refused — 1 (2016)416Approved — 7 (2017)Refused — 2 (2017)9Approved — 3 (2018)Refused — 3 (2018)618Approved — 4 (2019)Refused — 3 (2019)7Approved — 4 (2020)Refused — 1 (2020)520Approved — 14 (2021)Refused — 1 (2021)15Approved — 8 (2022)Refused — 1 (2022)922Approved — 13 (2023)Refused — 3 (2023)16Approved — 8 (2024)Refused — 2 (2024)1024Approved — 18 (2025)18Approved — 1 (2026)126
Approved Refused

Onshore wind decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (335)

SchemeMWStatusDecided
Dunside Wind Farm
EDF Energy · ECU00003436 · 33.2 mo to decide
108Awaiting Construction2026-03-24
Ceislein Wind Farm
RWE Renewables UK Limited · ECU00005174
77Application Submitted2026-03-13
Watchman Energy Park
Renewco Power · ECU00006030
120Application Submitted2026-03-12
Inveroykel Wind Farm
RWE Renewables UK Swindon Limited · ECU00005210
191Application Submitted2026-02-06
Creachan Wind Farm & BESS
RWE · ECU00005211
Application Submitted2026-02-05
Hare Hill Wind Farm Repowering
SSE Renewables · ECU00004967
130Application Submitted2026-01-26
Clashindarroch Wind Farm Extension
Infinergy · ECU00004695 · 35.2 mo to decide
138.6Awaiting Construction2025-12-18
Sclenteuch Wind Farm - Wind Farm
RES Limited · ECU00003318 · 41.2 mo to decide
54Awaiting Construction2025-12-16
Cloud Hill Wind Farm
Blue Energy Company / BayWa r.e. UK Limited · ECU00003461 · 26.4 mo to decide
56Awaiting Construction2025-12-16
Earlsburn Avenue - Earlsburn Wind Farm Extension
Naturalis Energy / REG Wind Power / Falck Renewables · ECU00004510 · 35.8 mo to decide
34Awaiting Construction2025-12-16
Golticlay Wind Farm, Bulreanrob - Wind Farm
RWE Renewables UK Swindon Limited · ECU00006095
Application Submitted2025-12-03
Mid Hill Wind Farm
Invenergy Services UK · ECU00005192
93.6Application Submitted2025-11-27
Bankend Rig III Wind Farm
Wilson Forrest Products Limited · ECU00004516 · 21.9 mo to decide
66Awaiting Construction2025-11-21
Knockcronal Wind Farm
Statkraft UK Limited · ECU00002181 · 47.6 mo to decide
59.4Awaiting Construction2025-11-05
Craiginmoddie Wind Farm
Energiekontor (UK) Limited · �ECU00002196 · 57.5 mo to decide
92.4Awaiting Construction2025-11-05
Beinneun II Windfarm
Beinneun 2 Ltd · ECU00004972
136.8Application Submitted2025-10-22
Uisenis Wind Farm
Uisenis Power Limited · 24.9 mo to decide
165Awaiting Construction2025-09-18
Crystal Rig Phase 1 Repowering
Fred Olsen Renewables · ECU00005089
72Application Submitted2025-09-17
Kyllachy Wind Farm - Wind Turbines
Wind Estate (UK) Limited · ECU00005153
78Application Submitted2025-09-05
Beinn Ghlas Wind Farm - Repowering
Nadara Limited (Beaufort Wind Limited) · 25/01240/PP
33.6Application Submitted2025-08-27
Windy Standard I Repower
Fred Olsen Renewables · ECU00003324 · 32.6 mo to decide
49.6Awaiting Construction2025-08-26
Sandy Knowe Wind Farm Extension
Executive Resource Group · ECU00003274 · 36.3 mo to decide
21.6Awaiting Construction2025-08-26
Millennium East
Renantis UK Limited · ECU00005013
49.6Application Submitted2025-08-13
Meall Dearg Wind Farm - Wind Farm
Energiekontor (UK) Limited · ECU00006049
147Application Submitted2025-08-11
Dorenell Extension Wind Farm
Galileo · ECU00004862
476.6Application Submitted2025-08-08
Blackhills Wind Farm
Koehler Renewable Energy · ECU00005136
43.2Application Submitted2025-08-07
Ballach Wind Farm
Energiekontor (UK) Limited · ECU00005219
144Application Submitted2025-08-06
Allt Domhain Wind Farm, Glenbarr - Wind Turbines
Energiekontor UK Limited · ECU00003231
64.8Application Submitted2025-07-31
Giants Burn Wind Farm-
Statkraft UK Limited · ECU00005007
50.4Application Submitted2025-07-15
Coille Beith - Wind Turbines
Statkraft UK Limited · ECU00005173
79.2Application Submitted2025-07-10
Teindland Wind Farm
European Energy A/S / Locogen Limited · ECU00004556
85Application Submitted2025-07-09
Teindland Wind Farm
European Energy A/S / Locogen Limited · ECU00004556
Application Submitted2025-07-09
Coille Linne Wind Farm- Wind Turbines
Energiekontor (UK) Limited · ECU00005163
108.5Application Submitted2025-06-18
Appin Wind Farm - Wind Farm
Statkraft UK Limited · ECU00003447
Application Submitted2025-06-12
Glen Lednock Wind Farm
Low Carbon Limited · ECU00004966
Application Submitted2025-06-11
High Brenfield Wind Farm
Low Carbon Limited · ECU00004961
66Application Submitted2025-06-10
Windburn Wind Farm
Octopus Energy / Wind 2 Limited · ECU00004782
65Application Submitted2025-06-05
Lairdmannoch Energy Park
Wind2 / Octopus Energy · ECU00004900
60Application Submitted2025-05-27
Back Fell Wind Farm
E Power Limited · ECU00004830
92.4Application Submitted2025-05-19
Burnside Bhlaraidh - Chrathaich Wind Farm
Muirden Energy Llp · ECU00004704 · 22.2 mo to decide
70Awaiting Construction2025-05-09
Breezy Hill, North Kyle Forest Estate - Wind Turbines
Brockwell Energy Limited · ECU00005060
100Application Submitted2025-05-08
Hagshaw Energy Cluster � Western Expansion
3R Energy Solutions Limited · ECU00004623
130Application Submitted2025-05-08
Tomchrasky Estate Wind farm
E Power Limited · ECU00004663 · 29.5 mo to decide
84Awaiting Construction2025-05-06
Ladyfield Renewable Energy Park
Ridge Clean Energy Limited · ECU00003291 · 15.4 mo to decide
58.5Awaiting Construction2025-05-02
South Kyle Wind Farm 2
Vattenfall · ECU00003429
92.4Application Submitted2025-05-02
Lynemore Wind Farm
Galileo Empower UK Limited · ECU00005105
100.8Application Submitted2025-05-01
Knockkippen Wind, Solar & Battery Farm
Falck Renewables / REG Windpower · ECU00004523 · 34.2 mo to decide
60Awaiting Construction2025-04-30
Carn Fearna Wind Farm
Statkraft UK · ECU00004851
84.6Application Submitted2025-04-15
Cnoc Buidhe Windfarm
Belltown Power Limited · ECU00004767
191.4Application Submitted2025-04-10
Ourack
Vattenfall · ECU00001999 · 29.2 mo to decide
105Awaiting Construction2025-03-25
Balblair Wind Farm
Wind Power North Two Limited · ECU00005055
36Application Submitted2025-03-14
Corr Chnoc Wind Farm
Galileo Green Energy Scotland Limited · ECU00006023
86.4Application Submitted2025-03-04
Blair Hill Wind Farm
RES Limited · ECU00004878
145Application Submitted2025-03-03
Clune Wind Farm - Wind Farm
Renewable Energy Systems · ECU00005038
187.2Application Submitted2025-03-03
Balnespick Wind Farm
Fred Olsen Renewables Limited · ECU00004904
55.8Application Submitted2025-02-20
Invershin Community Hall - Wind Farm & Battery Storage
Garvary Wind Farm Limited · ECU00003251 · 46 mo to decide
222Awaiting Construction2025-02-13
Allt an Tuir Renewable Energy Park
REG Windpower Limited / ESB Energy Limited · ECU00005008
59.4Application Submitted2025-02-06
Highland Wind Farm - Wind Farm
Highland Wind Farm Limited · ECU00005082
133Application Submitted2025-01-31
Mid Moile Wind Farm
EnergieKontor UK Limited · ECU00003405 · 35.5 mo to decide
99.4Awaiting Construction2025-01-30
Crosbie Wind Farm
Galileo Green Energy Scotland Limited (GGE Scotland) · ECU00004981
98Application Submitted2025-01-28
Glentarken Wind Farm
SSE Renewables Wind Farms UK Ltd · ECU00004700
104Application Submitted2025-01-21
Harestanes West Windfarm
ScottishPower Renewables · ECU00004778
84Application Submitted2025-01-20
Strath Oykel Wind Farm
Energiekontor (UK) Limited · ECU00003246 · 31.8 mo to decide
72.6Awaiting Construction2025-01-08
West Torrisdale Wind Farm
ESB Asset Development UK · ECU00002224
54Application Submitted2025-01-06
Pencloe Wind Farm - Wind Farm Extension
Pencloe Wind Farm · ECU00005185
22.5Application Submitted2024-12-18
Cruach Clenamacrie Wind Farm
Voltalia · ECU00004841
45Application Submitted2024-12-05
Loch Awe - Eredine Wind Farm
RWE Renewables UK Limited · ECU00004517
100Application Submitted2024-11-20
Glenvernoch Wind Farm
Energiekontor (UK) Limited · ECU00004892
86Application Submitted2024-11-12
Clachaig Glen
RWE UK · ECU00002103 · 31.7 mo to decide
60Awaiting Construction2024-11-05
M74 West Renewable Energy Park
Renewco Power · ECU00005019
165Application Submitted2024-09-24
Hollandmey Renewable Energy Development
Scottishpower Renewables · ECU00003353 · 33.9 mo to decide
50Awaiting Construction2024-09-16
Tweed Valley, Southern Uplands - Oliver Forest Wind Farm
Statkraft UK Limited · ECU00004669
50.4Application Submitted2024-08-30
Killean Wind Farm
RES Limited · ECU00004927
59.4Application Submitted2024-08-15
Lethans Wind Farm Extension
Banks Renewables · ECU00002221 · 31.5 mo to decide
66Awaiting Construction2024-08-08
Creag Riabhach Wind Farm Extension & Battery Storage
Creag Riabhach Wind Farm Limited · ECU00004487 · 25.9 mo to decide
12.6Awaiting Construction2024-07-05
Tom Na Clach - Wind Farm Extension
Infinergy Limited · ECU00003453 · 25.1 mo to decide
31.5Awaiting Construction2024-05-10
Brunt Hill Wind Farm & Battery Storage
E Power Limited · ECU00004654
129.6Application Submitted2024-05-08
Armadale Wind Farm
Brookfield Renewable UK · ECU00003455
43.2Application Withdrawn2024-05-07
Acheilidh Wind Farm (Previously known as Lairg III)
Energiekontor (UK) Limited · ECU00004528
79.2Application Submitted2024-05-07
Rowan Wind Farm
Energiekontor UK Limited · ECU00003230 · 26.7 mo to decide
85.8Awaiting Construction2024-04-26
Lees Hill Energy Park
Fred Olsen Renewables Limited · ECU00004571
36Application Submitted2024-04-16
Shinness Wind Farm
Shinness Wind Farm Limited · ECU00004597
105.6Application Submitted2024-04-15
Leithenwater Wind Energy Hub - Wind Farm
Belltown Power Limited · ECU00004619
85.8Application Submitted2024-04-04
Bunloinn Wind Farm
Energiekontor (UK) Limited · ECU00003304 · 24.1 mo to decide
66.6Awaiting Construction2024-04-02
Kellas Wind Farm
E Power Limited · ECU00005054
55.2Application Submitted2024-03-19
Dell Wind Farm 2
Dell Wind Farm Ltd (Coriolis Energy) · ECU00003440
59.4Application Submitted2024-03-11
Narachan Wind Farm
Energiekontor UK · ECU00001884 · 49.7 mo to decide
72.6Application Refused2024-03-08
Aultmore Forest - Buckie - Windfarm
Vattenfall · ECU00003365
105.6Application Submitted2024-02-28
Lethen Wind Farm Wind Turbines and Energy Storage
Fred Olsen Renewables Ltd · ECU00002216 · 25.1 mo to decide
102Application Refused2024-02-23
Cairn Duhie Wind Farm
Renewable Energy Systems (RES) · �ECU00003225 · 34.3 mo to decide
67.2Awaiting Construction2024-02-02
Faw Side Community Wind Farm
Community Windpower · ECU00001833 · 55 mo to decide
315Application Refused2023-12-22
Corriegarth 2
Corriegarth 2 Windfarm Limited (BayWa r.e. UK Limited) · �ECU00002175 · 35 mo to decide
67.2Awaiting Construction2023-12-20
Chleansaid Onshore Wind Farm
ESB · ECU00002031 · 20.5 mo to decide
96Awaiting Construction2023-12-15
Cloiche Wind Farm
Scottish & Southern (SSE) · ECU00002054 · 43.1 mo to decide
125Awaiting Construction2023-11-30
Penicuik, Moorfoot Hills - Torfichen Wind Farm
RES Limited · ECU00004661
108Application Submitted2023-11-28
Culachy Wind Farm
Fred Olsen Renewables Limited · ECU00003423
57.6Application Submitted2023-11-17
Newlands Hill Wind Energy Hub
Belltown Power Limited · ECU00004603
136Application Submitted2023-11-14
Hill of Fare - Hill of Fare Wind Farm & Battery Storage
RES Limited · ECU00004592
105.6Application Submitted2023-11-06
Kintradwell Lodge - Wind Farm
Renewable Energy System Limited · �ECU00002217 · 32.4 mo to decide
63Application Refused2023-11-03
Longcroft Wind Farm
Renewable Energy Systems · ECU00004774
125.4Application Submitted2023-10-31
Glendye Estate
Coriolis Energy/ ESB · ECU00000676 · 60.8 mo to decide
104Awaiting Construction2023-10-27
Vale of Leven Wind Farm
Coriolis Energy Limited · ECU00003468
70Application Submitted2023-10-17
Energy Isles Wind Farm
Energy Isles / Stratcraft · ECU00001844 · 53.3 mo to decide
126Awaiting Construction2023-10-02
Sanquhar 2 Community Wind Farm
Community Windpower · ECU00001801 · 53.4 mo to decide
308Under Construction2023-08-31
Clauchrie Windfarm
ScottishPower Renewables · ECU00002001 · 44.4 mo to decide
100Application Refused2023-08-31
Shepherd's Rig Wind Farm
Boralex/Infinergy · ECU00000735 · 56.1 mo to decide
81Awaiting Construction2023-08-21
Watten Wind Farm
EDF Energy Renewables · ECU00004509
47.6Application Submitted2023-08-14
Clashindarroch 2
Vattenfall · ECU00002002 · 43.6 mo to decide
77Awaiting Construction2023-08-11
Ditcher Law Wind Farm
E Power Ltd · ECU00004890
59.4Application Submitted2023-08-08
Glen Ullinish II - Wind Farm
Muirhall Energy Limited · ECU00004829
310.2Application Submitted2023-07-31
Kirkan Wind Farm
Coriolis Energy · ECU00001800 · 52.4 mo to decide
81.6Awaiting Construction2023-07-25
Rivox Wind Farm - Wind farm
Belltown Power Limited · ECU00003293
208Application Submitted2023-07-10
Bodinglee Wind Farm
Banks Group · ECU00004839
266Application Submitted2023-06-22
Ben Aketil Wind Farm - Repowered & Extended
Falck Renewables Limited · ECU00004552
59.4Application Submitted2023-06-09
Knockodhar Wind Farm
REG Knockodhar Limited · ECU00002153
100Application Submitted2023-05-26
Achany Extension Wind Farm
SSE Renewables · ECU00001930 · 22 mo to decide
76Awaiting Construction2023-05-22
Abhainn Dubh Wind Farm
E Power Limited · ECU00004732
58.8Application Submitted2023-05-19
Loch Liath Wind Farm
Statkraft Wind UK Limited · ECU00002182
85Application Submitted2023-04-28
Greenburn Wind Park
REG Windpower Limited · ECU00002037 · 36.8 mo to decide
67.2Awaiting Construction2023-04-21
Melvich Bay - Melvich Wind Energy Hub
Belltown Power Limited · ECU00004515
57.6Application Submitted2023-03-29
An Carr Dubh Wind Farm
Statkraft UK Limited · ECU00004781
85.8Application Submitted2023-03-22
Kennoxhead Wind Farm Extension II (Penbreck) (Phase 2)
Orsted Onshore Limited · ECU00003263 · 21.7 mo to decide
45.6Awaiting Construction2023-02-20
Artfield Forest Wind Farm
Statkraft UK · ECU00003245 · 22.6 mo to decide
67.2Awaiting Construction2023-02-10
Quantans Hill Wind Farm
Vattenfall Wind Power Limited · ECU00003399
96Application Submitted2023-01-27
Scawd Law Wind Farm
Fred Olsen Renewables · ECU00002111
48Application Submitted2022-12-22
Chesters - Millmoor Rig Wind Farm & Battery Energy Storage
ESB Asset Development UK Ltd · ECU00003426
78Application Submitted2022-11-28
Lorg Windfarm
RWE Npower Renewables · ECU00003283
96Application Submitted2022-11-12
Kirkton Energy Farm
Kirkton Wind Farm Limited · ECU00003244
52.8Application Submitted2022-11-09
Bloch Wind Farm & Battery Storage (Solway Bank Extension)
Renewable Energy Systems (RES) · ECU00003463
126Application Submitted2022-11-02
Rothes Wind Farm III
Fred Olsen Renewables · ECU00000474 · 44.6 mo to decide
132Awaiting Construction2022-10-22
Fetteresso Wind Farm (Mid Hill 3)
Fred Olsen Renewables · ECU00001851 · 39.6 mo to decide
42Awaiting Construction2022-09-21
Bhlaraidh Wind Farm Extension
SSE Renewables · ECU00001900 · 12.5 mo to decide
84Awaiting Construction2022-08-30
Kennoxhead Wind Farm (Phase 2)
Orsted Onshore Limited · �EC00002101 · 112.4 mo to decide
28Awaiting Construction2022-06-14
Craig Watch - Wind Farm & Battery Storage
Craig Watch Wind Farm Limited · ECU00002177
72.6Application Submitted2022-06-14
Teviot Wind Farm
Muirhall Energy Limited · ECU00003249
350Application Submitted2022-05-20
Limekiln Wind Farm (Extension)
Infinergy / Boralex · ECU00002070 · 23.7 mo to decide
21Operational2022-05-06
Clash Gour
EDF Energy Renewables/ Force 9 · ECU00000738 · 40 mo to decide
225Awaiting Construction2022-04-19
Grayside Wind Farm
Grayside WF · ECU00003446
147Application Submitted2022-03-31
Glenshero Wind Farm
RES/ SIMEC · ECU00000517 · 41.2 mo to decide
168Application Refused2022-03-04
Earraghail Renewable Energy Development
ScottishPower Renewables · ECU00003421
78Application Submitted2022-02-21
Heathland Wind Farm
EDF Energy Renewables · ECU00002218 · 12.5 mo to decide
80Awaiting Construction2022-02-09
Stornoway Wind Farm (second resubmission)
EDF Renewables UK / ESB · ECU00001850 · 31.5 mo to decide
196Awaiting Construction2022-01-05
Strathy Wood
E.ON Renewables · EC00005239 · 74.7 mo to decide
62.4Under Construction2021-12-08
Berry Burn Wind Farm (extension)
Statkraft Wind UK Limited · ECU00000718 · 16 mo to decide
37.8Awaiting Construction2021-12-08
Kilgallioch Windfarm (Extension)
ScottishPower Renewables · ECU00001996 · 23.8 mo to decide
50.4Under Construction2021-12-08
Carrick Windfarm
ScottishPower Renewables · ECU00003392
86Application Submitted2021-12-06
Stranoch 2
EDF Energy · ECU00000710 · 37.2 mo to decide
84Awaiting Construction2021-11-24
Douglas West Wind Farm (extension)
ScottishPower Renewables (UK) Limited · ECU00001836 · 31.2 mo to decide
78Under Construction2021-11-18
Cumberhead West Wind Farm
3R Energy Solutions Limited · ECU00002171 · 11.5 mo to decide
126Under Construction2021-11-18
Arecleoch Wind Farm (extension)
Scottish Power Renewables · ECU00001864 · 29.2 mo to decide
72.8Under Construction2021-11-16
Loganhead Wind Farm
Muirhall Energy Limited · ECU00002161
53.8Application Submitted2021-11-10
Blarghour Wind Farm
Coriolis Energy / ESB · EC00005267 · 41.5 mo to decide
84Awaiting Construction2021-10-29
Greystone Knowe Wind Farm - Wind Farm
Coriolis Energy Limited · ECU00003341
75Application Submitted2021-10-27
Tormsdale -Wind Farm
Arise AB / Lomond Energy · ECU00003335
50Application Submitted2021-10-12
North Kyle Energy Project
Brockwell Energy · ECU00001950 · 21.1 mo to decide
205.8Under Construction2021-06-30
Cloich Forest Wind Farm
EDF Energy Renewables · ECU00003288
63Application Submitted2021-06-30
Lethans Wind Farm
OnPath Energy Limited · ECU00001856 · 24.9 mo to decide
105.6Awaiting Construction2021-06-18
Daer Wind Farm
E.ON Climate & Renewables UK Developments · P/21/1014
100Application Submitted2021-05-26
Golticlay Wind Farm
RWE Renewables UK Limited · EC00003133 · 52.8 mo to decide
72.6Under Construction2021-03-24
Crystal Rig Wind Farm Phase IV
Fred Olsen Renewables · ECU00000607 · 33.8 mo to decide
48Under Construction2021-03-24
Windy Standard III Wind Farm (Brockloch Rig Phase 2)
Fred Olsen Renewables · ECU00000335 · 51.4 mo to decide
87.6Under Construction2021-03-23
Kennoxhead Wind Farm Extension (Phase 2)
Orsted Onshore Limited · ECU00002038 · 11.3 mo to decide
38.4Awaiting Construction2021-03-10
Lowther Hills (North Lowther Energy Initiative)
Forsa (formerly 2020 Renewables/ Buccleuch) · ECU00000426 · 42.9 mo to decide
147Appeal Refused2021-01-08
Troston Loch
EDF Energy Renewables · ECU00001785 · 21.9 mo to decide
67.2Awaiting Construction2020-12-18
Pauls Hill 2
Fred Olsen Renewables · ECU00000578 · 32.5 mo to decide
28Awaiting Construction2020-12-11
Harestanes South Windfarm Extension
ScottishPower Renewables · ECU00002185
45Application Submitted2020-12-07
Euchanhead Wind Farm
ScottishPower Renewables UK Limited · �ECU00002141
126Application Submitted2020-11-30
Scoop Hill Wind Farm
Community Wind Power Limited · �ECU00000533
525Application Submitted2020-11-12
Hopsrig Wind Farm
Muirhall Energy Limited · ECU00002160
79.2Application Submitted2020-10-23
High Constellation Wind Farm
BayWa r.e. UK Limited · ECU00001857 · 13 mo to decide
48Awaiting Construction2020-06-26
Fallago Rig 2 (extension)
EDF Energy Renewables · EC00003102 · 52.9 mo to decide
41Appeal Refused2020-06-25
Airigh Wind Farm
EDF Energy Renewables · ECU00000471 · 30.6 mo to decide
58.8Abandoned2020-03-20
Hagshaw Hill (Repowering)
Scottish Power Renewables · ECU00000737 · 14.8 mo to decide
84Awaiting Construction2020-02-26
Tangy 4 Wind Farm
Scottish & Southern (SSE) · ECU00000673 · 15.4 mo to decide
80Awaiting Construction2019-12-20
Killean
Renewable Energy Systems (RES) · EC00005266 · 36.3 mo to decide
56Revised2019-12-18
Sheirdrim Renewable Energy Development - Wind
ScottishPower Renewables · ECU00001957
114Appeal Refused2019-10-10
Harryburn Wind Farm
RWE · EC00005277 · 28.4 mo to decide
67Appeal Refused2019-09-27
Enoch Hill
E.ON Renewables · EC00005256 · 47.5 mo to decide
70Under Construction2019-09-13
Limekiln Wind Farm
Boralex/Infinergy · EC00005269 · 36.2 mo to decide
79.8Operational2019-06-21
Viking Wind Farm
Viking Energy Wind Farm · ECU00000723 · 6.3 mo to decide
443Operational2019-05-24
Dulater Hill Wind Farm
Ecotricity · 58.8 mo to decide
57.8Appeal Refused2019-05-24
Upper Sonachan Wind Farm
Ecotricity · EC00002081 · 42.8 mo to decide
64.6Appeal Refused2019-05-24
Birneyknowe Wind Farm
Banks Renewables · EC00002092 · 55.3 mo to decide
60Appeal Refused2018-12-21
Pencloe Wind Farm
North British Wind / Invenergy · EC00003106 · 45.3 mo to decide
81Under Construction2018-12-06
Yell Wind Farm
Energy Isles · ECU00000725
126Revised2018-11-13
Heathland Wind Farm
EDF Energy Renewables (formerly Partnerships for Renewables) · EC00003124 · 32.3 mo to decide
57.8Revised2018-10-26
West Garty Windfarm
West Garty Renewables · EC00002075 · 46.6 mo to decide
54Appeal Refused2018-10-19
Sandy Knowe Wind Farm
ERG · ECU00000660
81.6Operational2018-08-16
Caplich Wind Farm
Muirhall Energy · EC00002088 · 39.5 mo to decide
68Appeal Refused2018-04-27
Strathy South
Scottish and Southern Energy (SSE) · EC00003113 · 110.8 mo to decide
208Under Construction2018-04-27
Lethans Wind Farm
Banks Renewables · EC00002086 · 36.3 mo to decide
88Revised2018-03-23
Chirmorie Wind Farm
Corolis Energy/ ESB · EC00002071 · 27.5 mo to decide
80Awaiting Construction2018-03-16
Whitelaw Brae Wind Farm
Thrive Renewables · EC00002090 · 34.6 mo to decide
57Under Construction2017-12-07
Beaw Field Wind Farm
Peel Wind Farms · EC00003121 · 19.5 mo to decide
59.5Awaiting Construction2017-11-30
Hadyard Hill extension
Scottish and Southern Energy (SSE) · EC00003118
88Application Withdrawn2017-11-21
Braemore
EDF · EC00002100 · 82.3 mo to decide
54Planning Permission Expired2017-10-27
Crossburns Wind Farm
West Coast Energy · 36.2 mo to decide
75Appeal Refused2017-10-06
Cairn Duhie
Renewable Energy Systems (RES) · EC00002087 · 47 mo to decide
60Revised2017-10-06
Gordonbush (extension)
Scottish and Southern Energy (SSE) · EC00003105 · 28 mo to decide
47Operational2017-09-29
Benbrack Wind Farm
E.ON Renewables / Red Rock Power Limited · EC00002082 · 33.8 mo to decide
67.1Operational2017-09-15
South Kyle Wind Farm
Vattenfall · EC00003109 · 46 mo to decide
240Operational2017-06-30
Creggan Wind Farm
Burcote Wind · EC00002102 · 42.3 mo to decide
54Appeal Refused2017-06-23
Hill of Towie II Wind Farm
Renewable Energy Systems (RES) · 43.5 mo to decide
48Planning Permission Expired2017-06-16
Millennium South
Falck Renewables/West Coast Energy Ltd · EC00002077 · 32.5 mo to decide
35Revised2017-02-03
Inch Moor Wind Farm
Ecotricity · EC00003183
51.2Application Withdrawn2016-11-24
Keirs Hill (Sclenteuch) Wind Farm
Renewable Energy Systems (RES) · 35.8 mo to decide
57.8Revised2016-11-22
Drum Hollistan Wind Farm
Muirden Energy · ECU00000243
51Revised2016-10-20
Aikengall IIa Community Wind Farm
Community Windpower · 32.6 mo to decide
81.7Operational2016-10-19
Whitelee Windfarm Extension Phase 3
Scottish Power Renewables · 50.2 mo to decide
12Appeal Refused2016-10-19
Creag Riabhach Wind Farm
ERG · EC00002078 · 33.4 mo to decide
92.4Operational2016-10-17
Kype Muir Wind Farm Extension
Banks Renewables · EC00002083 · 23.2 mo to decide
67.2Operational2016-09-16
Linfairn Wind Farm
Willow Wind Energy · EC00004192 · 33.7 mo to decide
54.4Appeal Withdrawn2016-07-20
Cloich Forest Wind Farm
EDF Energy Renewables (formerly Partnerships for Renewables) · WIN-140-1 · 44.8 mo to decide
54Revised2016-07-08
Stranoch Wind Farm
EDF · EC00005254 · 41.4 mo to decide
72Revised2016-07-08
Dorenell Wind Farm (extension)
EDF Energy Renewables · EC00003111 · 17.7 mo to decide
174.9Abandoned2016-06-02
Quantans Hill Wind Farm
E.ON Climate and Renewables UK Limited
57Application Withdrawn2016-04-28
Macritch Hill Wind Farm
Eneco / ScottishWater
59.4Application Withdrawn2016-04-28
Cruach Brenfield Wind Farm
Dulas · EC00002094
59.4Application Withdrawn2016-03-14
Harestanes Wind Farm Extension
Scottish Power Renewables · 25.1 mo to decide
14Application Refused2015-12-17
Sallachy Wind Farm
WKN Windkraft Nord AG (WKN) · 46.9 mo to decide
66Revised2015-11-17
Glencassley Wind Farm
Scottish and Southern Energy (SSE) · 40.2 mo to decide
69Application Refused2015-11-17
Longburn Wind Farm
Burcote Wind · EC00002080
72Application Withdrawn2015-11-05
Talladh-a-Bheithe Wind Farm
Eventus Duurzaam
75Application Withdrawn2015-10-30
Uisenis/Eishken (Muaitheabhal) (Southern Extension)
EDF & AMEC (Lewis Wind Power) · EC00002096 · 26.9 mo to decide
21.6Revised2015-09-08
Allt Duine Wind Farm
RWE npower · EC00003192 · 53.2 mo to decide
93Application Refused2015-07-30
Limekiln Wind Farm
Infinergy · EC00003170 · 31.2 mo to decide
72Revised2015-07-23
Kennoxhead Wind Farm
Orsted Onshore Limited · �EC00002101 · 29.7 mo to decide
62Under Construction2015-07-23
Crystal Rig Wind Farm Phase III
Fred Olsen Renewables · 24.1 mo to decide
13.8Operational2015-06-18
Black Law Extension - 1b
Scottish Power Renewables · 49.2 mo to decide
15Operational2015-06-17
Beinneun Windfarm Extension
Octopus Investments/Blue Energy · EC00002095 · 7.6 mo to decide
23.8Operational2015-06-02
Musdale Wind Farm
Ventient (formerly Infinis)
64Application Withdrawn2015-05-22
Sandy Knowe Wind Farm
Burcote Wind · 26.4 mo to decide
90Revised2015-02-18
Afton Wind Farm
InfraRed Capital Partners/ E.on · 119.4 mo to decide
50Operational2014-10-16
Nathro Hill Wind Farm
Eurowind UK
61Application Withdrawn2014-10-15
Middle Muir Wind Farm
Banks Renewables · CL/12/0056 · 31.6 mo to decide
51Operational2014-09-26
Glenmorie Wind Farm
Wind Energy (Glenmorie) Ltd · 33.3 mo to decide
134Application Refused2014-08-21
Sanquhar 2 Community Windfarm - withdrawn
Community Windpower · EC00002070
19.8Revised2014-08-18
Clyde Wind Farm Extension (Clyde 2)
Scottish and Southern Energy (SSE)/ GIB · EC00003160 · 33.4 mo to decide
172.8Operational2014-07-23
Dersalloch
Scottish Power Renewables · 107.8 mo to decide
69Operational2014-07-23
Harburnhead Wind Farm
Gresham House · 30.6 mo to decide
51.7Operational2014-07-09
Fauch Hill Wind Farm
European Forest Resources Group · 28.4 mo to decide
69Application Refused2014-07-08
Stronelairg Wind Farm
Scottish and Southern Energy (SSE) · EC00005242 · 23.2 mo to decide
227.7Operational2014-06-06
Newfield
Wind Power Ltd · 56.1 mo to decide
63Application Refused2014-06-06
Kype Muir Wind Farm
Banks Renewables · EK/11/0256 · 33.4 mo to decide
88.4Operational2014-05-22
Rowantree Wind Farm
RWE npower · 52.5 mo to decide
69Application Refused2014-05-16
Ewe Hill (extension)
Scottish Power Renewables · 121.5 mo to decide
36.8Operational2014-05-16
Fairburn Extension
Scottish and Southern Energy (SSE)
36Application Withdrawn2014-02-26
Dalnessie Wind Farm
Scottish and Southern Energy (SSE)
67.5Application Withdrawn2014-02-26
Moy Wind Farm (2nd Application)
Eneco · 9.1 mo to decide
66Operational2014-01-24
Bhlaraidh (previously Balmacaan)
Scottish and Southern Energy (SSE) · 18.6 mo to decide
110Operational2014-01-17
Harelaw Renewable Energy Park
Gamesa Energy · 52.3 mo to decide
117Application Refused2013-09-27
Brown Muir Wind Farm
Vento Ludens
57Revised2013-08-15
Glenkirk
Eurus Energy · 92.6 mo to decide
93Application Refused2013-06-14
Dunbeath
Dunbeath Wind Energy Ltd (Agents are West Coast Energy) · 93.8 mo to decide
66Application Refused2013-06-07
Girthgate Wind Farm
Community Windpower · EC00005270
81.6Appeal Withdrawn2013-06-01
Aikengall II, Wester Dod Community Wind Farm
Community Windpower · 41.9 mo to decide
60.8Operational2013-03-01
Kilgallioch wind farm
Scottish Power Renewables · 35.6 mo to decide
239Operational2013-02-21
Beinneun
Octopus Investments/Blue Energy · 12 mo to decide
85Operational2012-11-04
Lochluichart (Extension)
Infinergy · EC00005211 · 13.1 mo to decide
18Operational2012-10-02
Pairc Windfarm
Scottish and Southern Energy (SSE)
94Application Withdrawn2012-08-29
Galawhistle
Ventient (formerly Infinis) · 28.9 mo to decide
66Operational2012-08-08
Spittal Hill
Spittal Hill Windfarm · 07/00217/S36CA · 61.7 mo to decide
75Revised2012-06-13
Viking Wind Farm
Viking Energy / Scottish and Southern · 34.5 mo to decide
370Revised2012-04-04
Shira Wind Farm
Natural Power · 06/00554/ELSA36
79Application Withdrawn2012-02-23
Dorenell Wind Farm (Previously Site A and B Scaut Hill)
EDF Energy Renewables/ Infinergy · EC00003173 · 43.9 mo to decide
177Operational2012-01-03
Uisenis/Eishken (Muaitheabhal) (East Extension)
EDF & AMEC (Lewis Wind Power) · EC00005223 · 28.1 mo to decide
21.6Revised2011-12-08
Strathy North
Scottish and Southern Energy (SSE) · 58.3 mo to decide
67.7Operational2011-11-22
Waterhead Moor
Scottish and Southern Energy (SSE)
72.5Application Withdrawn2011-10-31
Druim Ba Wind Farm
Druim Ba Sustainable Energy · 6.2 mo to decide
69Revised2011-09-20
Harelaw Renewable Energy Park Wind Turbines
Gamesa Energy · 2009/0304/EBC
80Revised2011-07-04
Corbie Shank
Renewable Development Company Ltd
150Application Withdrawn2011-06-29
Black Law Extension - 1a
Scottish Power Renewables · 37.8 mo to decide
48.4Operational2011-03-22
Blackcraig
Blue Energy · 05/n/2005 · 65.7 mo to decide
52.9Operational2011-03-22
Careston Estate
Renewable Energy Systems (RES)
52Application Withdrawn2011-02-09
Dunmaglass Wind Farm
Scottish and Southern Energy (SSE) · 70.5 mo to decide
94Operational2010-12-29
Fallago Rig
EDF Energy Renewables · 65.8 mo to decide
144Operational2010-11-09
Rannoch Wind Farm
Talladh an Bheith & Craiganour Estates
75Application Withdrawn2010-06-09
Tullich Wind Farm
Savills
180Application Withdrawn2010-06-09
Ewe Hill
Scottish Power Renewables · IEC3/107 · 74 mo to decide
13.8Operational2010-06-07
Harrow's Law
Scottish and Southern Energy (SSE)
111Revised2010-04-28
Uisenis/Eishken (Muaitheabhal) Wind Farm
EDF & AMEC (Lewis Wind Power) · EC00005222 · 61.4 mo to decide
118.8Revised2010-01-14
Baillie Wind Farm
Baillie Windfarm Ltd · 04/00342/S36CA · 66 mo to decide
52.5Operational2010-01-12
Whitelee Windfarm Extension phase 2
Scottish Power · WHX/02/040/0162 · 6.5 mo to decide
109Operational2009-12-12
Kilbraur Windfarm Farlary - Extension
Falck Renewables · 09/00111/S36SU · 8.6 mo to decide
20Operational2009-12-01
Berry Burn
Statkraft · 58.7 mo to decide
66.7Operational2009-08-10
Millennium Extension II
West Coast Energy Ltd/Falck Renewables · 7.1 mo to decide
15Operational2009-08-10
Whitelee Windfarm Extension Phase 1
Scottish Power Renewables · 13.6 mo to decide
108Operational2009-05-20
Camster
E.ON UK · 48.3 mo to decide
50Operational2009-01-13
Lochluichart
Eneco · EC00005210 · 37 mo to decide
51Operational2008-12-22
Kyle Windfarm
AMEC · IEC3/73 · 47.8 mo to decide
255Application Refused2008-10-24
Crystal Rig Wind Farm Phase 2a
Fred Olsen Renewables · 12.5 mo to decide
138Operational2008-07-30
Clyde Wind Farm
Scottish and Southern Energy (SSE)/ Greencoat UK Wind · 45.6 mo to decide
350Operational2008-07-21
Earlshaugh Wind Farm
Wind Energy Ltd
55.2Abandoned2008-06-25
Carraig Gheal
Green Power · 42.9 mo to decide
46Operational2008-06-13
Muckla Moor
Scottish and Southern Energy (SSE)
249Application Withdrawn2008-06-11
Mark Hill
Force 9 Energy · 33.4 mo to decide
56Operational2008-06-01
Arecleoch Windfarm
Scottish Power Renewables · 26 mo to decide
120Operational2008-06-01
Bracco / Black Hill
Airtricity
72.5Application Withdrawn2008-04-24
Lewis Wind Farm (Barvas Moor)
Lewis WindPower (a joint venture between British Energy Renewables and AMEC WIND) · 41.6 mo to decide
652Application Refused2008-04-21
Leithope Forest
Npower Renewables
70Application Withdrawn2008-04-16
Scoolary
British Energy
120Application Withdrawn2008-04-16
Kilpatrick Hills
Airtricity
60Application Withdrawn2008-04-16
Nutberry
West Coast Energy · CL/05/0667
60Application Withdrawn2008-04-16
Gordonbush
Scottish and Southern Energy (SSE) · 57.8 mo to decide
70Operational2008-04-09
Griffin Wind farm
Greenpower (Griffin) Ltd · 45.1 mo to decide
156Operational2008-01-31
Harestanes
Scottish Power Renewables · 41.8 mo to decide
136Operational2007-09-10
Brochloch Rig (formerly Windy Standard II)
Fred Olsen Renewables · 02/n/20002 · 62.9 mo to decide
90Operational2007-03-13
Invercassley Windfarm
Airtricity · 05/00400/FULSU · 13.5 mo to decide
55Appeal Refused2006-12-13
Abercairney
Catamount Energy Ltd c/o Force 9 · 32.9 mo to decide
66Appeal Refused2006-10-05
Spireslack Windfarm
Hargreaves Resources
59.6Application Withdrawn2006-05-26
Limmer Hill
West Coast Energy (for RDC/Falk) · CL/05/0563
99Application Withdrawn2006-05-10
Broubster Forest
Scottish and Southern Energy (SSE)
116Application Withdrawn2006-05-02
Clashindarroch
AMEC · IEC3/67 · 32.4 mo to decide
129Revised2006-05-01
Whitelee
CRE Energy/ Scottish Power · 2002/0001/EB · 50.2 mo to decide
322Operational2006-04-01
Stacain
Wind Prospect · 05/00770/DET · 8.3 mo to decide
48Appeal Refused2005-12-10
Knowehead
British Energy Renewables Ltd · 04/01664/FUL · 10.8 mo to decide
60Application Refused2005-07-04
Mid Hill - Phase II
Fred Olsen Renewables · SO30179PF · 27.7 mo to decide
18.4Operational2005-06-03
Mid Hill I
Fred Olsen Renewables · SO30179PF · 27.7 mo to decide
57.5Operational2005-06-03
Crystal Rig Extension II
Natural Power Consultants · 12.8 mo to decide
20.7Operational2005-05-25
Greenock Wind Farm
Airtricity · 22.9 mo to decide
55Appeal Refused2005-04-01
Farr Wind Farm
Innogy (formerly RWE npower) · 24.8 mo to decide
92Operational2004-10-05
Braes O'Doune
Greencoat UK Wind · S/02/01320/NST · 23.2 mo to decide
72Operational2004-10-05
Aultmore Wind Farm
AMEC · IEC 3/68 (S.E. ref)
62Revised2004-03-03
Black Law
Scottish Power Renewables · 20.8 mo to decide
124Operational2004-02-13
Hadyard Hill
Scottish and Southern Energy (SSE) · 03/01745/DEEM · 7.1 mo to decide
120Operational2003-12-29
Paul's Hill and Extension
Fred Olsen Renewables · IEC3/99 · 18 mo to decide
65Operational2003-03-31
Crystal Rig Phase 1
Fred Olsen Renewables · 01/00269/FUL · 21.7 mo to decide
62.5Operational2003-01-22
Rothes Wind (Cairn Uish)
Natural Power Consultants · 15.8 mo to decide
50.6Operational2003-01-21
Laudale Wind Farm
Wind Energy
75Abandoned
North Nesting Wind, Shetland
Scottish and Southern Energy (SSE)
250Abandoned
Hanna Wind Farm
Wind Energy
81Abandoned
Golticlay Wind Farm 2
RWE Renewables UK Limited
13.2No Application Required
Glen Calvie Wind Farm, Ardgay
Wind Energy
69Abandoned
Forse Wind Farm
Wind Energy
60Abandoned
Hill of Fare Wind Farm
Infinergy
150Abandoned

Does Scottish Government (S36) approve onshore wind schemes?

Yes — of the 173 onshore wind schemes Scottish Government (S36) has decided, 80% were approved (138 granted, 35 refused). The UK-wide rate for onshore wind is 68%.

How long does a onshore wind scheme application take in Scottish Government (S36)?

The median time from application to decision is 33.7 months, against a UK median of 11.5 months for onshore wind. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much onshore wind capacity has Scottish Government (S36) consented?

12,247 MW has been consented across 138 approved schemes, with 3,613 MW refused. A further 122 applications awaits a decision.

Other technologies in Scottish Government (S36)

Solar in Scottish Government (S36)Battery storage in Scottish Government (S36)

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.