Renewable sites › Dungavel Hill
Dungavel Hill
Dungavel Hill is operational in South Lanarkshire with a recorded capacity of 29.9 MW, and has been generating since 2015-08-28.
Planning and build timeline
| Application submitted | 2006-02-17 |
| Permission granted | 2009-12-01 45 months after submission |
| Operational | 2015-08-28 69 months after consent |
South Lanarkshire’s record on onshore wind
South Lanarkshire has decided 49 onshore wind schemes and approved 73%, taking a median of 15.9 months. See every onshore wind scheme decision in South Lanarkshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Bankend Rig Wind Onshore · Operational | 14.3 | 4.1 km |
Kype Muir Wind Farm Extension Wind Onshore · Operational | 67.2 | 4.7 km |
Kype Muir Wind Farm Wind Onshore · Operational | 88.4 | 4.7 km |
Mill Rig Wind Farm Wind Onshore · Under Construction | 36 | 5.7 km |
Auchrobert Wind Farm Wind Onshore · Operational | 36 | 7.4 km |
Strathaven Airfield Solar Photovoltaics · Operational | — | 7.9 km |
Calder Water Community Wind Farm Wind Onshore · Operational | 28 | 7.9 km |
West Browncastle Wind Onshore · Operational | 30 | 9 km |
How big is Dungavel Hill?
Dungavel Hill has a recorded installed capacity of 29.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Dungavel Hill?
REPD records the operator as John Laing Environmental Assets Group. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Dungavel Hill approved and built?
The application was submitted on 2006-02-17. Permission was granted on 2009-12-01, 45 months later. The site became operational on 2015-08-28, 69 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4362.
Novarly Parcel · official public data, read properly · parcel.novarly.com