Renewable sites › King's Yard
King's Yard
King's Yard is an operational 3 MW biomass plant in Newham, generating since 25 July 2012. Planning permission was granted on 10 March 2009, 11 months after submission. Operator of record: Suez Energy Services.
Planning and build timeline
| Application submitted | 8 April 2008 |
| Permission granted | 10 March 2009 11 months after submission |
| Operational | 25 July 2012 41 months after consent |
Screening a site of your own?
Redline runs the record on your own boundary in Newham: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with King's Yard’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Urban agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Solar Photovoltaics · Operational | 1 | 1.5 km |
Solar Photovoltaics · Under Construction | 0.24 | 4.1 km |
Solar Photovoltaics · Operational | 0.16 | 4.6 km |
Solar Photovoltaics · Operational | 1 | 5.3 km |
Solar Photovoltaics · Under Construction | 0.22 | 5.9 km |
Wind Onshore · Operational | 2.2 | 6 km |
Sewage Sludge Digestion · Operational | 5.8 | 6 km |
EfW Incineration · Operational | 35 | 6.3 km |
How big is King's Yard?
King's Yard has a recorded installed capacity of 3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates King's Yard?
REPD records the operator as Suez Energy Services. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was King's Yard approved and built?
The application was submitted on 8 April 2008. Permission was granted on 10 March 2009, 11 months later. The site became operational on 25 July 2012, 41 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 87.