Renewable sites › Holly Street - Solar PV Panels
Holly Street - Solar PV Panels
Holly Street - Solar PV Panels is operational in Hackney with a recorded capacity of 0.16 MW, and has been generating since 2021-12-31.
Planning and build timeline
| Application submitted | 2021-08-25 |
| Permission granted | 2023-02-21 18 months after submission |
| Operational | 2021-12-31 |
What this site sits on
The recorded coordinate falls on land surveyed as Urban agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
King's Yard Biomass (dedicated) · Operational | 3 | 4.6 km |
Bywaters� Materials Recovery Facility Solar Array Solar Photovoltaics · Operational | 1 | 5 km |
SELCHP ERF EfW Incineration · Operational | 35 | 6.7 km |
Dolphin Square - Solar panels Solar Photovoltaics · Under Construction | — | 7.7 km |
Advent Way - Solar Panels Solar Photovoltaics · Operational | 0.18 | 8 km |
Leyes Road - New SEN School Solar Photovoltaics · Under Construction | 0.24 | 8.4 km |
Edmonton EcoPark EfW EfW Incineration · Operational | 55 | 8.5 km |
Thameside DC Solar Photovoltaics · Operational | 1 | 8.8 km |
How big is Holly Street - Solar PV Panels?
Holly Street - Solar PV Panels has a recorded installed capacity of 0.16 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Holly Street - Solar PV Panels?
REPD records the operator as London Borough of Hackney. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Holly Street - Solar PV Panels approved and built?
The application was submitted on 2021-08-25. Permission was granted on 2023-02-21, 18 months later. The site became operational on 2021-12-31.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 9632.