Renewable sites › Kincraig - Solar Farm and battery storage system
Kincraig - Solar Farm and battery storage system
Kincraig - Solar Farm and battery storage system is under construction in Aberdeenshire with a recorded capacity of 21 MW.
Planning and build timeline
| Application submitted | 2022-04-14 |
| Permission granted | 2022-10-18 6 months after submission |
| Operational | not recorded |
Aberdeenshire’s record on solar
Aberdeenshire has decided 39 solar farms and approved 100%, taking a median of 2.1 months. See every solar farm decision in Aberdeenshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Kincraig - Solar Farm and battery storage system Battery · Under Construction | — | 0 km |
Hill of Fiddes Wind Onshore · Operational | 6.9 | 2.8 km |
Balmcassie Commercial Park - Anaerobic digestion plant Anaerobic Digestion · Under Construction | 3.5 | 6.5 km |
Black Dog Landfill Gas · Operational | 2.2 | 10.3 km |
Upper Ardgrain Wind Farm Wind Onshore · Operational | 2.4 | 10.4 km |
Tarbothill Landfill Site Landfill Gas · Operational | 2.2 | 11.2 km |
Skelmonae Wind Farm Wind Onshore · Operational | 3.2 | 14.2 km |
Farburn Place - Battery Energy Storage Facility Battery · Under Construction | 30 | 14.4 km |
How big is Kincraig - Solar Farm and battery storage system?
Kincraig - Solar Farm and battery storage system has a recorded installed capacity of 21 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Kincraig - Solar Farm and battery storage system?
REPD records the operator as Renewable Connections Developments Limited. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Kincraig - Solar Farm and battery storage system approved and built?
The application was submitted on 2022-04-14. Permission was granted on 2022-10-18, 6 months later. The site is recorded as under construction and has no operational date yet.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 11177.