Novarly ParcelRenewable sites

Renewable sitesHill of Fiddes

Hill of Fiddes

Hill of Fiddes is operational in Aberdeenshire with a recorded capacity of 6.9 MW, and has been generating since 2010-02-20.

6.9 MW
Capacity
as recorded in REPD
Operational
Status
since 2010-02-20
Wind Onshore
Technology
Infinis, previously Broadview Energy
Aberdeenshire
Authority
Scotland

Planning and build timeline

Application submitted2007-09-03
Permission granted2008-04-01
7 months after submission
Operational2010-02-20
23 months after consent

Aberdeenshire’s record on onshore wind

Aberdeenshire has decided 118 onshore wind schemes and approved 69%, taking a median of 12.7 months. See every onshore wind scheme decision in Aberdeenshire

Other built sites within 15 km

SiteMWDistance
Kincraig - Solar Farm and battery storage system
Solar Photovoltaics · Under Construction
212.8 km
Kincraig - Solar Farm and battery storage system
Battery · Under Construction
2.8 km
Balmcassie Commercial Park - Anaerobic digestion plant
Anaerobic Digestion · Under Construction
3.57.6 km
Black Dog
Landfill Gas · Operational
2.210.5 km
Upper Ardgrain Wind Farm
Wind Onshore · Operational
2.411 km
Tarbothill Landfill Site
Landfill Gas · Operational
2.211.2 km
Courtstone Wind Turbine
Wind Onshore · Operational
2.312.8 km
Farburn Place - Battery Energy Storage Facility
Battery · Under Construction
3013 km

How big is Hill of Fiddes?

Hill of Fiddes has a recorded installed capacity of 6.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Hill of Fiddes?

REPD records the operator as Infinis, previously Broadview Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Hill of Fiddes approved and built?

The application was submitted on 2007-09-03. Permission was granted on 2008-04-01, 7 months later. The site became operational on 2010-02-20, 23 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3968.