Planning and build timeline

Application submitted2007-07-06
Permission granted2009-02-24
20 months after submission
Operational2009-12-20
10 months after consent

Aberdeenshire’s record on onshore wind

Aberdeenshire has decided 118 onshore wind schemes and approved 69%, taking a median of 12.7 months. See every onshore wind scheme decision in Aberdeenshire

Other built sites within 15 km

SiteMWDistance
Methlick Farmers Wind Energy Project
Wind Onshore · Operational
123.3 km
Hill of Skilmafilly Cloffrickford (Denmore) Wind Farm
Wind Onshore · Operational
6.93.9 km
Courtstone Wind Turbine
Wind Onshore · Operational
2.35.4 km
Hill of Balquhindachy extension
Wind Onshore · Operational
1.76.5 km
Haddo
Wind Onshore · Operational
4.67.1 km
Upper Ardgrain Wind Farm
Wind Onshore · Operational
2.48 km
St John's Well
Wind Onshore · Operational
2.48.2 km
St Johns Wells Wind Cluster Extension
Wind Onshore · Operational
3.28.7 km

How big is Skelmonae Wind Farm?

Skelmonae Wind Farm has a recorded installed capacity of 3.2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Skelmonae Wind Farm?

REPD records the operator as Private Developer. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Skelmonae Wind Farm approved and built?

The application was submitted on 2007-07-06. Permission was granted on 2009-02-24, 20 months later. The site became operational on 2009-12-20, 10 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3075.