Novarly ParcelRenewable sites

Renewable sitesHolmside Hall

Holmside Hall

Holmside Hall is operational in County Durham with a recorded capacity of 2.8 MW, and has been generating since 2004-06-01.

2.8 MW
Capacity
as recorded in REPD
Operational
Status
since 2004-06-01
Wind Onshore
Technology
E.ON UK
County Durham
Authority
England

Planning and build timeline

Application submitted2002-03-31
Permission granted2003-01-16
10 months after submission
Operational2004-06-01
16 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 4 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

County Durham’s record on onshore wind

County Durham has decided 30 onshore wind schemes and approved 63%, taking a median of 10.5 months. See every onshore wind scheme decision in County Durham

Other built sites within 15 km

SiteMWDistance
Langley Moor
Wind Onshore · Operational
82.6 km
Chapman's Well
Landfill Gas · Operational
13.5 km
Green Croft Solar Farm
Solar Photovoltaics · Operational
53.8 km
Greencroft Estate Turbines
Wind Onshore · Operational
44.6 km
PG4 St Bedes Power Generation (Extension)
Landfill Gas · Operational
27.5 km
PG4 St Bedes Power Generation
Landfill Gas · Operational
27.6 km
PG4 St Bedes Power Generation (Extension 2)
Landfill Gas · Operational
17.7 km
Kibblesworth Landfill Site
Landfill Gas · Operational
2.37.8 km

How big is Holmside Hall?

Holmside Hall has a recorded installed capacity of 2.8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Holmside Hall?

REPD records the operator as E.ON UK. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Holmside Hall approved and built?

The application was submitted on 2002-03-31. Permission was granted on 2003-01-16, 10 months later. The site became operational on 2004-06-01, 16 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3494.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council