Novarly ParcelRenewable sites

Renewable sitesKeadby Wind Farm

Keadby Wind Farm

Keadby Wind Farm is operational in North Lincolnshire with a recorded capacity of 68 MW, and has been generating since 2015-02-26.

68 MW
Capacity
as recorded in REPD
Operational
Status
since 2015-02-26
Wind Onshore
Technology
Scottish and Southern Energy (SSE)
North Lincolnshire
Authority
England

Planning and build timeline

Application submitted2003-10-24
Permission granted2008-02-28
52 months after submission
Operational2015-02-26
84 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 2 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

North Lincolnshire’s record on onshore wind

North Lincolnshire has decided 8 onshore wind schemes and approved 38%, taking a median of 14.6 months. See every onshore wind scheme decision in North Lincolnshire

Other built sites within 15 km

SiteMWDistance
North Moor Farm AD Plant (Farm AD)
Anaerobic Digestion · Operational
44.6 km
Flixborough Industrial Estate
Solar Photovoltaics · Operational
54.7 km
Grange
Wind Onshore · Operational
12.35.1 km
Bagmoor
Wind Onshore · Operational
166.6 km
Twin Rivers
Wind Onshore · Operational
28.79.4 km
Roxby Gas to Energy
Landfill Gas · Operational
8.59.8 km
Goole Fields
Wind Onshore · Operational
32.810.3 km
Goole Fields ll Wind Farm
Wind Onshore · Operational
34.910.9 km

How big is Keadby Wind Farm?

Keadby Wind Farm has a recorded installed capacity of 68 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Keadby Wind Farm?

REPD records the operator as Scottish and Southern Energy (SSE). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Keadby Wind Farm approved and built?

The application was submitted on 2003-10-24. Permission was granted on 2008-02-28, 52 months later. The site became operational on 2015-02-26, 84 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4260.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council