Keadby Wind Farm
Keadby Wind Farm is an operational 68 MW onshore wind farm in North Lincolnshire, generating since 26 February 2015. Planning permission was granted on 28 February 2008, 52 months after submission. Operator of record: Scottish and Southern Energy (SSE).
Planning and build timeline
| Application submitted | 24 October 2003 |
| Permission granted | 28 February 2008 52 months after submission |
| Operational | 26 February 2015 84 months after consent |
Screening a site of your own?
North Lincolnshire approves 38% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Keadby Wind Farm’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 2 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
North Lincolnshire’s record on onshore wind
North Lincolnshire has decided 8 onshore wind schemes and approved 38%, taking a median of 14.6 months. See every onshore wind scheme decision in North Lincolnshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Anaerobic Digestion · Operational | 4 | 4.6 km |
Solar Photovoltaics · Operational | 5 | 4.7 km |
Wind Onshore · Operational | 12.3 | 5.1 km |
Wind Onshore · Operational | 16 | 6.6 km |
Wind Onshore · Operational | 28.7 | 9.4 km |
Landfill Gas · Operational | 8.5 | 9.8 km |
Wind Onshore · Operational | 32.8 | 10.3 km |
Wind Onshore · Operational | 34.9 | 10.9 km |
How big is Keadby Wind Farm?
Keadby Wind Farm has a recorded installed capacity of 68 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Keadby Wind Farm?
REPD records the operator as Scottish and Southern Energy (SSE). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Keadby Wind Farm approved and built?
The application was submitted on 24 October 2003. Permission was granted on 28 February 2008, 52 months later. The site became operational on 26 February 2015, 84 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4260.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode