Novarly ParcelRenewable sites

Renewable sitesGrange

Grange

Grange is operational in North Lincolnshire with a recorded capacity of 12.3 MW, and has been generating since 2015-12-15.

12.3 MW
Capacity
as recorded in REPD
Operational
Status
since 2015-12-15
Wind Onshore
Technology
Octopus Investements/Blue Energy
North Lincolnshire
Authority
England

Planning and build timeline

Application submitted2010-11-02
Permission granted2014-01-07
38 months after submission
Operational2015-12-15
23 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 2 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

North Lincolnshire’s record on onshore wind

North Lincolnshire has decided 8 onshore wind schemes and approved 38%, taking a median of 14.6 months. See every onshore wind scheme decision in North Lincolnshire

Other built sites within 15 km

SiteMWDistance
Flixborough Industrial Estate
Solar Photovoltaics · Operational
52 km
Bagmoor
Wind Onshore · Operational
162.5 km
Roxby Gas to Energy
Landfill Gas · Operational
8.55 km
Keadby Wind Farm
Wind Onshore · Operational
685.1 km
Winterton Landfill Site - Ground Mounted Solar PV Arrays
Solar Photovoltaics · Under Construction
56.2 km
Winterton Landfill Site
Landfill Gas · Operational
3.86.5 km
North Moor Farm AD Plant (Farm AD)
Anaerobic Digestion · Operational
49.4 km
Raventhorpe Farm
Solar Photovoltaics · Operational
3811.7 km

How big is Grange?

Grange has a recorded installed capacity of 12.3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Grange?

REPD records the operator as Octopus Investements/Blue Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Grange approved and built?

The application was submitted on 2010-11-02. Permission was granted on 2014-01-07, 38 months later. The site became operational on 2015-12-15, 23 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4069.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council