Twin Rivers is an operational 28.7 MW onshore wind farm in Doncaster, generating since 3 August 2016. Planning permission was granted on 5 January 2009, 60 months after submission. Operator of record: NTR.
Planning and build timeline
| Application submitted | 20 January 2004 |
| Permission granted | 5 January 2009 60 months after submission |
| Operational | 3 August 2016 91 months after consent |
Screening a site of your own?
Doncaster approves 80% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Twin Rivers’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Doncaster’s record on onshore wind
Doncaster has decided 5 onshore wind schemes and approved 80%, taking a median of 49.2 months. See every onshore wind scheme decision in Doncaster →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 44 | 2.6 km |
Solar Photovoltaics · Operational | 5 | 3.6 km |
Solar Photovoltaics · Operational | 0.27 | 4.6 km |
Solar Photovoltaics · Under Construction | 0.18 | 4.6 km |
Wind Onshore · Operational | 32.8 | 6.5 km |
Landfill Gas · Operational | 2.7 | 7.2 km |
Landfill Gas · Operational | 1.2 | 7.4 km |
Landfill Gas · Operational | 1.4 | 7.4 km |
How big is Twin Rivers?
Twin Rivers has a recorded installed capacity of 28.7 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Twin Rivers?
REPD records the operator as NTR. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Twin Rivers approved and built?
The application was submitted on 20 January 2004. Permission was granted on 5 January 2009, 60 months later. The site became operational on 3 August 2016, 91 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3657.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode