Goole Fields
Goole Fields is operational in East Riding of Yorkshire with a recorded capacity of 32.8 MW, and has been generating since 2014-08-11.
Planning and build timeline
| Application submitted | 2003-04-01 |
| Permission granted | 2003-09-01 5 months after submission |
| Operational | 2014-08-11 131 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 1 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
East Riding of Yorkshire’s record on onshore wind
East Riding of Yorkshire has decided 55 onshore wind schemes and approved 82%, taking a median of 7.8 months. See every onshore wind scheme decision in East Riding of Yorkshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Goole Fields ll Wind Farm Wind Onshore · Operational | 34.9 | 1.2 km |
Thorne Farm Solar Photovoltaics · Operational | 5 | 4.5 km |
Tween Bridge Windfarm Wind Onshore · Operational | 44 | 5.7 km |
Twin Rivers Wind Onshore · Operational | 28.7 | 6.5 km |
Rusholme Grange Battery · Operational | 40 | 7.9 km |
Croda Chemicals Europe Wind Onshore · Operational | 3 | 8 km |
Rusholme Wind Farm Wind Onshore · Operational | 24 | 8.1 km |
Sixpenny Wood Windfarm Wind Onshore · Operational | 33 | 9.5 km |
How big is Goole Fields?
Goole Fields has a recorded installed capacity of 32.8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Goole Fields?
REPD records the operator as RWE npower. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Goole Fields approved and built?
The application was submitted on 2003-04-01. Permission was granted on 2003-09-01, 5 months later. The site became operational on 2014-08-11, 131 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4373.