Renewable sites › Flixborough Industrial Estate
Flixborough Industrial Estate
Flixborough Industrial Estate is operational in North Lincolnshire with a recorded capacity of 5 MW, and has been generating since 2017-03-01.
Planning and build timeline
| Application submitted | 2015-04-08 |
| Permission granted | 2016-10-11 18 months after submission |
| Operational | 2017-03-01 5 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 2 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
North Lincolnshire’s record on solar
North Lincolnshire has decided 28 solar farms and approved 89%, taking a median of 1.8 months. See every solar farm decision in North Lincolnshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Bagmoor Wind Onshore · Operational | 16 | 2 km |
Grange Wind Onshore · Operational | 12.3 | 2 km |
Keadby Wind Farm Wind Onshore · Operational | 68 | 4.7 km |
Roxby Gas to Energy Landfill Gas · Operational | 8.5 | 5.2 km |
Winterton Landfill Site - Ground Mounted Solar PV Arrays Solar Photovoltaics · Under Construction | 5 | 7.4 km |
Winterton Landfill Site Landfill Gas · Operational | 3.8 | 7.5 km |
North Moor Farm AD Plant (Farm AD) Anaerobic Digestion · Operational | 4 | 8.3 km |
Raventhorpe Farm Solar Photovoltaics · Operational | 38 | 10 km |
How big is Flixborough Industrial Estate?
Flixborough Industrial Estate has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Flixborough Industrial Estate?
REPD records the operator as NESF (formerly INRG Solar). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Flixborough Industrial Estate approved and built?
The application was submitted on 2015-04-08. Permission was granted on 2016-10-11, 18 months later. The site became operational on 2017-03-01, 5 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5204.