Bagmoor

Bagmoor is an operational 16 MW onshore wind farm in North Lincolnshire, generating since 1 July 2009. Planning permission was granted on 1 April 2006, 14 months after submission. Operator of record: Munich Re (previously Wind Prospect).

16 MW
Capacity
as recorded in REPD
Operational
Status
since 1 July 2009
Wind Onshore
Technology
Munich Re (previously Wind Prospect)
North Lincolnshire
Authority
England

Planning and build timeline

Application submitted15 January 2005
Permission granted1 April 2006
14 months after submission
Operational1 July 2009
39 months after consent

Screening a site of your own?

RedlineUK · £39

North Lincolnshire approves 38% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Bagmoor’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

North Lincolnshire’s record on onshore wind

North Lincolnshire has decided 8 onshore wind schemes and approved 38%, taking a median of 14.6 months. See every onshore wind scheme decision in North Lincolnshire

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
52 km
Wind Onshore · Operational
12.32.5 km
Landfill Gas · Operational
8.53.2 km
Landfill Gas · Operational
3.85.7 km
Solar Photovoltaics · Under Construction
55.8 km
Wind Onshore · Operational
686.6 km
Solar Photovoltaics · Operational
389.4 km
Anaerobic Digestion · Operational
410.3 km

How big is Bagmoor?

Bagmoor has a recorded installed capacity of 16 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Bagmoor?

REPD records the operator as Munich Re (previously Wind Prospect). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Bagmoor approved and built?

The application was submitted on 15 January 2005. Permission was granted on 1 April 2006, 14 months later. The site became operational on 1 July 2009, 39 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2928.