Onshore wind planning in North Lincolnshire

North Lincolnshire has decided 8 onshore wind schemes and approved 38% of them, taking a median of 14.6 months to decide. Consented capacity: 96 MW. 3 applications still awaiting a decision.

38%
Approved
3 granted · 5 refused
14.6 mo
Median decision
UK 11.5 mo
96 MW
Consented
94 MW refused
4
Appeals
1 allowed on appeal

How North Lincolnshire compares

Against the 75 UK authorities with 5+ onshore wind decisions, North Lincolnshire sits in the 9th percentile for approval rate (30 points below the England average) and the 48th percentile for speed.

Decisions by year

35Refused — 1 (2011)111Refused — 1 (2012)112Refused — 1 (2013)113Approved — 1 (2014)114Refused — 1 (2015)115
Approved Refused

Onshore wind decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (11)

SchemeMWStatusDecided
Foxhills Industrial Estate - Wind Turbine
E-Energies · PA/2025/1560
Application Submitted2025-12-23
Old River Don Wind Farm
REG Windpower · WF/2014/0710 · 14.8 mo to decide
18Application Refused2015-09-23
Grange
Octopus Investements/Blue Energy · WF/2010/1242 · 38.2 mo to decide
12.3Operational2014-01-07
Ironstone Quarry Wind Farm
Waste Recycling Group · WF/2011/0528 · 24.6 mo to decide
7.5Application Refused2013-06-05
Saxby Wold Wind Farm
RWE Npower Renewables · WF/2011/0734 · 7.6 mo to decide
36Appeal Refused2012-02-08
Bradken UK
Wind Direct · PA/2011/0497 · 3 mo to decide
2.5Application Refused2011-08-08
Saxby Wold (Brigg Road)
Npower Renewables · WF/2009/0657 · 19.2 mo to decide
45Revised2011-01-07
Flixborough Grange Farmhouse
Grange Wind Farm Ltd · WF/2009/0573 · 8.6 mo to decide
14Revised2010-01-29
Keadby Wind Farm
Scottish and Southern Energy (SSE) · 2003/1630 · 52.2 mo to decide
68Operational2008-02-28
Bagmoor
Munich Re (previously Wind Prospect) · 14.5 mo to decide
16Operational2006-04-01
Elsham Wind Farm
E.ON UK · WF/2004/1414 · 10.4 mo to decide
30Appeal Refused2005-06-24

Does North Lincolnshire approve onshore wind schemes?

Yes — of the 8 onshore wind schemes North Lincolnshire has decided, 38% were approved (3 granted, 5 refused). The UK-wide rate for onshore wind is 68%.

How long does a onshore wind scheme application take in North Lincolnshire?

The median time from application to decision is 14.6 months, against a UK median of 11.5 months for onshore wind. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much onshore wind capacity has North Lincolnshire consented?

96 MW has been consented across 3 approved schemes, with 94 MW refused. A further 3 applications awaits a decision.

Other technologies in North Lincolnshire

Solar in North LincolnshireBattery storage in North Lincolnshire

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.