Renewable sites › ICI No2 (Teesport) Landfill
ICI No2 (Teesport) Landfill
ICI No2 (Teesport) Landfill is an operational 1 MW landfill gas site in Redcar and Cleveland, generating since 1 September 2021. Planning permission was granted on 24 September 2021, 48 months after submission. Operator of record: Highfield Environmental.
Planning and build timeline
| Application submitted | 9 October 2017 |
| Permission granted | 24 September 2021 48 months after submission |
| Operational | 1 September 2021 |
Screening a site of your own?
Redline runs the record on your own boundary in Redcar and Cleveland: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with ICI No2 (Teesport) Landfill’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Urban agricultural land.
- Nutrient-neutrality catchment — Teesmouth and Cleveland Coast SPA/Ramsar
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Anaerobic Digestion · Operational | 5.1 | 2.1 km |
Biomass (dedicated) · Operational | 35.2 | 4.7 km |
EfW Incineration · Operational | 49 | 4.7 km |
Biomass (dedicated) · Under Construction | 40 | 4.8 km |
Solar Photovoltaics · Operational | 0.18 | 5.5 km |
Anaerobic Digestion · Operational | 4.8 | 6 km |
Solar Photovoltaics · Under Construction | 0.17 | 6.1 km |
EfW Incineration · Operational | 21 | 6.6 km |
How big is ICI No2 (Teesport) Landfill?
ICI No2 (Teesport) Landfill has a recorded installed capacity of 1 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates ICI No2 (Teesport) Landfill?
REPD records the operator as Highfield Environmental. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was ICI No2 (Teesport) Landfill approved and built?
The application was submitted on 9 October 2017. Permission was granted on 24 September 2021, 48 months later. The site became operational on 1 September 2021.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6517.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode