Imperial Park

Imperial Park is an operational 5.1 MW anaerobic digestion plant in Redcar and Cleveland, generating since 5 December 2016. Planning permission was granted on 16 October 2014, 3 months after submission. Operator of record: BioConstruct.

5.1 MW
Capacity
as recorded in REPD
Operational
Status
since 5 December 2016
Anaerobic Digestion
Technology
BioConstruct
Redcar and Cleveland
Authority
England

Planning and build timeline

Application submitted8 July 2014
Permission granted16 October 2014
3 months after submission
Operational5 December 2016
26 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Redcar and Cleveland: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Imperial Park’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Urban agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Landfill Gas · Operational
12.1 km
Biomass (dedicated) · Under Construction
403 km
Solar Photovoltaics · Operational
0.183.3 km
Anaerobic Digestion · Operational
4.84 km
EfW Incineration · Operational
19.25 km
EfW Incineration · Operational
215 km
EfW Incineration · Operational
105 km
EfW Incineration · Operational
20.15.1 km

How big is Imperial Park?

Imperial Park has a recorded installed capacity of 5.1 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Imperial Park?

REPD records the operator as BioConstruct. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Imperial Park approved and built?

The application was submitted on 8 July 2014. Permission was granted on 16 October 2014, 3 months later. The site became operational on 5 December 2016, 26 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 348.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode