Imperial Park

Imperial Park is operational in Redcar and Cleveland with a recorded capacity of 5.1 MW, and has been generating since 2016-12-05.

5.1 MW
Capacity
as recorded in REPD
Operational
Status
since 2016-12-05
Anaerobic Digestion
Technology
BioConstruct
Redcar and Cleveland
Authority
England

Planning and build timeline

Application submitted2014-07-08
Permission granted2014-10-16
3 months after submission
Operational2016-12-05
26 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Urban agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
ICI No2 (Teesport) Landfill
Landfill Gas · Operational
12.1 km
Port Clarence Biomass Plant
Biomass (dedicated) · Under Construction
403 km
Albert Road Rooftop Solar Panels
Solar Photovoltaics · Operational
0.183.3 km
Teesside Green Energy Plant (Waste AD)
Anaerobic Digestion · Operational
4.84 km
Teesside EfW (extension)
EfW Incineration · Operational
105 km
North East Energy Recovery Centre (adjacent to Teesside EfW)
EfW Incineration · Operational
215 km
Teesside EfW
EfW Incineration · Operational
19.25 km
Haverton Hill Incinerator
EfW Incineration · Operational
20.15.1 km

How big is Imperial Park?

Imperial Park has a recorded installed capacity of 5.1 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Imperial Park?

REPD records the operator as BioConstruct. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Imperial Park approved and built?

The application was submitted on 2014-07-08. Permission was granted on 2014-10-16, 3 months later. The site became operational on 2016-12-05, 26 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 348.