Port Clarence Biomass Plant is a 40 MW biomass plant under construction in Stockton-on-Tees. Planning permission was granted on 23 February 2010, 1 months after submission. Operator of record: Glennmont Partners.
Planning and build timeline
| Application submitted | 14 January 2010 |
| Permission granted | 23 February 2010 1 months after submission |
| Operational | not recorded |
Screening a site of your own?
Redline runs the record on your own boundary in Stockton-on-Tees: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Port Clarence Biomass Plant’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Urban agricultural land.
- Nutrient-neutrality catchment — Teesmouth and Cleveland Coast SPA/Ramsar
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Anaerobic Digestion · Operational | 4.8 | 1.3 km |
Solar Photovoltaics · Operational | 0.18 | 1.6 km |
EfW Incineration · Operational | 20.1 | 2 km |
EfW Incineration · Operational | 10 | 2.1 km |
EfW Incineration · Operational | 21 | 2.1 km |
EfW Incineration · Operational | 19.2 | 2.1 km |
EfW Incineration · Operational | 12 | 2.8 km |
Anaerobic Digestion · Operational | 5.1 | 3 km |
How big is Port Clarence Biomass Plant?
Port Clarence Biomass Plant has a recorded installed capacity of 40 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Port Clarence Biomass Plant?
REPD records the operator as Glennmont Partners. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Port Clarence Biomass Plant approved and built?
The application was submitted on 14 January 2010. Permission was granted on 23 February 2010, 1 months later. The site is recorded as under construction and has no operational date yet.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 110.