Port Clarence Biomass Plant is under construction in Stockton-on-Tees with a recorded capacity of 40 MW.

40 MW
Capacity
as recorded in REPD
Under Construction
Status
no operational date
Biomass (dedicated)
Technology
Glennmont Partners
Stockton-on-Tees
Authority
England

Planning and build timeline

Application submitted2010-01-14
Permission granted2010-02-23
1 months after submission
Operationalnot recorded

What this site sits on

The recorded coordinate falls on land surveyed as Urban agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Teesside Green Energy Plant (Waste AD)
Anaerobic Digestion · Operational
4.81.3 km
Albert Road Rooftop Solar Panels
Solar Photovoltaics · Operational
0.181.6 km
Haverton Hill Incinerator
EfW Incineration · Operational
20.12 km
Teesside EfW (extension)
EfW Incineration · Operational
102.1 km
North East Energy Recovery Centre (adjacent to Teesside EfW)
EfW Incineration · Operational
212.1 km
Teesside EfW
EfW Incineration · Operational
19.22.1 km
Billingham Chemical Works
EfW Incineration · Operational
122.8 km
Imperial Park
Anaerobic Digestion · Operational
5.13 km

How big is Port Clarence Biomass Plant?

Port Clarence Biomass Plant has a recorded installed capacity of 40 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Port Clarence Biomass Plant?

REPD records the operator as Glennmont Partners. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Port Clarence Biomass Plant approved and built?

The application was submitted on 2010-01-14. Permission was granted on 2010-02-23, 1 months later. The site is recorded as under construction and has no operational date yet.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 110.