Novarly ParcelRenewable sites

Renewable sitesPort Clarence Biomass Plant

Port Clarence Biomass Plant

Port Clarence Biomass Plant is a 40 MW biomass plant under construction in Stockton-on-Tees. Planning permission was granted on 23 February 2010, 1 months after submission. Operator of record: Glennmont Partners.

40 MW
Capacity
as recorded in REPD
Under Construction
Status
no operational date
Biomass (dedicated)
Technology
Glennmont Partners
Stockton-on-Tees
Authority
England

Planning and build timeline

Application submitted14 January 2010
Permission granted23 February 2010
1 months after submission
Operationalnot recorded

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Stockton-on-Tees: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Port Clarence Biomass Plant’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Urban agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Anaerobic Digestion · Operational
4.81.3 km
Solar Photovoltaics · Operational
0.181.6 km
EfW Incineration · Operational
20.12 km
EfW Incineration · Operational
102.1 km
EfW Incineration · Operational
212.1 km
EfW Incineration · Operational
19.22.1 km
EfW Incineration · Operational
122.8 km
Anaerobic Digestion · Operational
5.13 km

How big is Port Clarence Biomass Plant?

Port Clarence Biomass Plant has a recorded installed capacity of 40 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Port Clarence Biomass Plant?

REPD records the operator as Glennmont Partners. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Port Clarence Biomass Plant approved and built?

The application was submitted on 14 January 2010. Permission was granted on 23 February 2010, 1 months later. The site is recorded as under construction and has no operational date yet.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 110.