Novarly ParcelRenewable sites

Renewable sitesTeesside Green Energy Plant (Waste AD)

Teesside Green Energy Plant (Waste AD)

Teesside Green Energy Plant (Waste AD) is an operational 4.8 MW anaerobic digestion plant in Middlesbrough, generating since 20 February 2015. Planning permission was granted on 11 July 2011, 4 months after submission. Operator of record: B F BIO GAS.

4.8 MW
Capacity
as recorded in REPD
Operational
Status
since 20 February 2015
Anaerobic Digestion
Technology
B F BIO GAS
Middlesbrough
Authority
England

Planning and build timeline

Application submitted28 February 2011
Permission granted11 July 2011
4 months after submission
Operational20 February 2015
43 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Middlesbrough: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Teesside Green Energy Plant (Waste AD)’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Urban agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
0.181.2 km
Biomass (dedicated) · Under Construction
401.3 km
EfW Incineration · Operational
20.11.7 km
EfW Incineration · Operational
101.9 km
EfW Incineration · Operational
19.21.9 km
EfW Incineration · Operational
211.9 km
EfW Incineration · Operational
122.1 km
Anaerobic Digestion · Operational
5.14 km

How big is Teesside Green Energy Plant (Waste AD)?

Teesside Green Energy Plant (Waste AD) has a recorded installed capacity of 4.8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Teesside Green Energy Plant (Waste AD)?

REPD records the operator as B F BIO GAS. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Teesside Green Energy Plant (Waste AD) approved and built?

The application was submitted on 28 February 2011. Permission was granted on 11 July 2011, 4 months later. The site became operational on 20 February 2015, 43 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 385.