Renewable sites › Teesside Green Energy Plant (Waste AD)
Teesside Green Energy Plant (Waste AD)
Teesside Green Energy Plant (Waste AD) is operational in Middlesbrough with a recorded capacity of 4.8 MW, and has been generating since 2015-02-20.
Planning and build timeline
| Application submitted | 2011-02-28 |
| Permission granted | 2011-07-11 4 months after submission |
| Operational | 2015-02-20 43 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Urban agricultural land.
- Nutrient-neutrality catchment — Teesmouth and Cleveland Coast SPA/Ramsar
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Albert Road Rooftop Solar Panels Solar Photovoltaics · Operational | 0.18 | 1.2 km |
Port Clarence Biomass Plant Biomass (dedicated) · Under Construction | 40 | 1.3 km |
Haverton Hill Incinerator EfW Incineration · Operational | 20.1 | 1.7 km |
Teesside EfW (extension) EfW Incineration · Operational | 10 | 1.9 km |
North East Energy Recovery Centre (adjacent to Teesside EfW) EfW Incineration · Operational | 21 | 1.9 km |
Teesside EfW EfW Incineration · Operational | 19.2 | 1.9 km |
Billingham Chemical Works EfW Incineration · Operational | 12 | 2.1 km |
Imperial Park Anaerobic Digestion · Operational | 5.1 | 4 km |
How big is Teesside Green Energy Plant (Waste AD)?
Teesside Green Energy Plant (Waste AD) has a recorded installed capacity of 4.8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Teesside Green Energy Plant (Waste AD)?
REPD records the operator as B F BIO GAS. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Teesside Green Energy Plant (Waste AD) approved and built?
The application was submitted on 2011-02-28. Permission was granted on 2011-07-11, 4 months later. The site became operational on 2015-02-20, 43 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 385.
Novarly Parcel · official public data, read properly · parcel.novarly.com