North East Energy Recovery Centre (adjacent to Teesside EfW)
North East Energy Recovery Centre (adjacent to Teesside EfW) is an operational 21 MW energy-from-waste plant in Stockton-on-Tees, generating since 30 April 2014. Planning permission was granted on 30 October 2008, 3 months after submission. Operator of record: SITA UK.
Planning and build timeline
| Application submitted | 31 July 2008 |
| Permission granted | 30 October 2008 3 months after submission |
| Operational | 30 April 2014 66 months after consent |
Screening a site of your own?
Redline runs the record on your own boundary in Stockton-on-Tees: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with North East Energy Recovery Centre (adjacent to Teesside EfW)’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Urban agricultural land.
- Nutrient-neutrality catchment — Teesmouth and Cleveland Coast SPA/Ramsar
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
EfW Incineration · Operational | 10 | 0 km |
EfW Incineration · Operational | 19.2 | 0 km |
EfW Incineration · Operational | 20.1 | 0.3 km |
EfW Incineration · Operational | 12 | 1.2 km |
Anaerobic Digestion · Operational | 4.8 | 1.9 km |
Biomass (dedicated) · Under Construction | 40 | 2.1 km |
Solar Photovoltaics · Operational | 0.18 | 3 km |
Solar Photovoltaics · Operational | 5 | 4 km |
How big is North East Energy Recovery Centre (adjacent to Teesside EfW)?
North East Energy Recovery Centre (adjacent to Teesside EfW) has a recorded installed capacity of 21 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates North East Energy Recovery Centre (adjacent to Teesside EfW)?
REPD records the operator as SITA UK. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was North East Energy Recovery Centre (adjacent to Teesside EfW) approved and built?
The application was submitted on 31 July 2008. Permission was granted on 30 October 2008, 3 months later. The site became operational on 30 April 2014, 66 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 925.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode