North East Energy Recovery Centre (adjacent to Teesside EfW) is an operational 21 MW energy-from-waste plant in Stockton-on-Tees, generating since 30 April 2014. Planning permission was granted on 30 October 2008, 3 months after submission. Operator of record: SITA UK.

21 MW
Capacity
as recorded in REPD
Operational
Status
since 30 April 2014
EfW Incineration
Technology
SITA UK
Stockton-on-Tees
Authority
England

Planning and build timeline

Application submitted31 July 2008
Permission granted30 October 2008
3 months after submission
Operational30 April 2014
66 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Stockton-on-Tees: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with North East Energy Recovery Centre (adjacent to Teesside EfW)’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Urban agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
EfW Incineration · Operational
100 km
EfW Incineration · Operational
19.20 km
EfW Incineration · Operational
20.10.3 km
EfW Incineration · Operational
121.2 km
Anaerobic Digestion · Operational
4.81.9 km
Biomass (dedicated) · Under Construction
402.1 km
Solar Photovoltaics · Operational
0.183 km
Solar Photovoltaics · Operational
54 km

How big is North East Energy Recovery Centre (adjacent to Teesside EfW)?

North East Energy Recovery Centre (adjacent to Teesside EfW) has a recorded installed capacity of 21 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates North East Energy Recovery Centre (adjacent to Teesside EfW)?

REPD records the operator as SITA UK. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was North East Energy Recovery Centre (adjacent to Teesside EfW) approved and built?

The application was submitted on 31 July 2008. Permission was granted on 30 October 2008, 3 months later. The site became operational on 30 April 2014, 66 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 925.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode