Novarly ParcelRenewable sites

Renewable sitesWilton International

Wilton International

Wilton International is operational in Redcar and Cleveland with a recorded capacity of 35.2 MW, and has been generating since 2007-03-26.

35.2 MW
Capacity
as recorded in REPD
Operational
Status
since 2007-03-26
Biomass (dedicated)
Technology
UK Wood Recycling
Redcar and Cleveland
Authority
England

Planning and build timeline

Application submitted2006-09-06
Permission granted2006-11-07
2 months after submission
Operational2007-03-26
5 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 4 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Wilton 11 EfW
EfW Incineration · Operational
490 km
Land at Woodhouse Farm
Solar Photovoltaics · Operational
53.8 km
ICI No2 (Teesport) Landfill
Landfill Gas · Operational
14.7 km
Kirkleatham Street - Solar Panel Array
Solar Photovoltaics · Under Construction
0.175.7 km
Imperial Park
Anaerobic Digestion · Operational
5.15.9 km
Teeside Offshore Wind Farm
Wind Offshore · Operational
628.7 km
Albert Road Rooftop Solar Panels
Solar Photovoltaics · Operational
0.188.9 km
Port Clarence Biomass Plant
Biomass (dedicated) · Under Construction
409 km

How big is Wilton International?

Wilton International has a recorded installed capacity of 35.2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Wilton International?

REPD records the operator as UK Wood Recycling. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Wilton International approved and built?

The application was submitted on 2006-09-06. Permission was granted on 2006-11-07, 2 months later. The site became operational on 2007-03-26, 5 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 35.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council