Huntington Water Treatment Works

Huntington Water Treatment Works is an operational 7.2 MW solar farm in Cheshire West and Chester, generating since 24 July 2019. Planning permission was granted on 24 April 2018, 5 months after submission. Operator of record: United Utilities.

7.2 MW
Capacity
as recorded in REPD
Operational
Status
since 24 July 2019
Solar Photovoltaics
Technology
United Utilities
Cheshire West and Chester
Authority
England

Planning and build timeline

Application submitted28 November 2017
Permission granted24 April 2018
5 months after submission
Operational24 July 2019
15 months after consent

Screening a site of your own?

RedlineUK · £39

Cheshire West and Chester approves 95% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Huntington Water Treatment Works’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Cheshire West and Chester’s record on solar

Cheshire West and Chester has decided 39 solar farms and approved 95%, taking a median of 1.7 months. See every solar farm decision in Cheshire West and Chester

Other built sites within 15 km

SiteMWDistance
Biomass (dedicated) · Operational
0.37.4 km
Landfill Gas · Operational
67.9 km
Landfill Gas · Operational
1.67.9 km
Solar Photovoltaics · Operational
0.2210.2 km
Battery · Operational
10011.3 km
Battery · Operational
5711.9 km
Battery · Under Construction
5712.3 km
Solar Photovoltaics · Operational
3.812.4 km

How big is Huntington Water Treatment Works?

Huntington Water Treatment Works has a recorded installed capacity of 7.2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Huntington Water Treatment Works?

REPD records the operator as United Utilities. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Huntington Water Treatment Works approved and built?

The application was submitted on 28 November 2017. Permission was granted on 24 April 2018, 5 months later. The site became operational on 24 July 2019, 15 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6532.