Renewable sites › Gowy Landfill Site
Gowy Landfill Site
Gowy Landfill Site is operational in Cheshire West and Chester with a recorded capacity of 1.6 MW, and has been generating since 1996-05-01.
Planning and build timeline
| Application submitted | 1994-09-06 |
| Permission granted | 1994-12-13 3 months after submission |
| Operational | 1996-05-01 17 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 4 agricultural land.
- Green Belt — Cheshire West and Chester
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Gowy Landfill Site, Cheshire (Extension) Landfill Gas · Operational | 6 | 0 km |
Longlooms Road East - Solar panels Solar Photovoltaics · Operational | 0.22 | 4.4 km |
Plot 8 Protos/Ince Marshes EfW Incineration · Under Construction | 35 | 5.1 km |
Ince Bio Power Advanced Conversion Technologies · Operational | 21.5 | 5.1 km |
S P & G Blything, Cross Lanes - Biomass Boiler Biomass (dedicated) · Operational | 0.3 | 7.4 km |
Huntington Water Treatment Works Solar Photovoltaics · Operational | 7.2 | 7.9 km |
Frodsham Marsh Wind Onshore · Operational | 50.4 | 8.2 km |
Native River Battery · Operational | 57 | 8.2 km |
How big is Gowy Landfill Site?
Gowy Landfill Site has a recorded installed capacity of 1.6 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Gowy Landfill Site?
REPD records the operator as Waste Recycling Group. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Gowy Landfill Site approved and built?
The application was submitted on 1994-09-06. Permission was granted on 1994-12-13, 3 months later. The site became operational on 1996-05-01, 17 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 546.