Honington Solar Farm

Honington Solar Farm is operational in West Suffolk with a recorded capacity of 13.6 MW, and has been generating since 2014-03-31.

13.6 MW
Capacity
as recorded in REPD
Operational
Status
since 2014-03-31
Solar Photovoltaics
Technology
NextEnergy Solar Fund (NESF)
West Suffolk
Authority
England

Planning and build timeline

Application submitted2012-08-22
Permission granted2012-12-10
4 months after submission
Operational2014-03-31
16 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

West Suffolk’s record on solar

West Suffolk has decided 29 solar farms and approved 97%, taking a median of 2.9 months. See every solar farm decision in West Suffolk

Other built sites within 15 km

SiteMWDistance
Raf Honington Solar Farm
Solar Photovoltaics · Under Construction
2.2 km
Ingham North Solar
Solar Photovoltaics · Operational
14.25.8 km
British Sugar - Bury
Anaerobic Digestion · Operational
510.4 km
Lackford Landfill Scheme
Landfill Gas · Operational
1.211.5 km
Easlea Road - Solar Photovoltaic Panels
Solar Photovoltaics · Operational
0.6211.5 km
West Suffolk College, Out Risbygate Street - Solar Panels
Solar Photovoltaics · Under Construction
0.5511.8 km
Thetford Biomass Power Station
Biomass (dedicated) · Operational
38.512.9 km
Lackford Estate Solar Park
Solar Photovoltaics · Operational
20.913.4 km

How big is Honington Solar Farm?

Honington Solar Farm has a recorded installed capacity of 13.6 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Honington Solar Farm?

REPD records the operator as NextEnergy Solar Fund (NESF). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Honington Solar Farm approved and built?

The application was submitted on 2012-08-22. Permission was granted on 2012-12-10, 4 months later. The site became operational on 2014-03-31, 16 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1757.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council