Thetford Biomass Power Station

Thetford Biomass Power Station is an operational 38.5 MW biomass plant in Breckland, generating since 2 October 1998. Planning permission was granted on 5 May 1995, 10 months after submission. Operator of record: Energy Power Resources.

38.5 MW
Capacity
as recorded in REPD
Operational
Status
since 2 October 1998
Biomass (dedicated)
Technology
Energy Power Resources
Breckland
Authority
England

Planning and build timeline

Application submitted23 June 1994
Permission granted5 May 1995
10 months after submission
Operational2 October 1998
41 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Breckland: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Thetford Biomass Power Station’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Non Agricultural agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Under Construction
11.2 km
Solar Photovoltaics · Operational
13.612.9 km
Solar Photovoltaics · Operational
14.214.5 km
Solar Photovoltaics · Operational
1014.8 km
Battery · Operational
7.514.8 km
Solar Photovoltaics · Operational
0.3414.9 km
Anaerobic Digestion · Operational
114.9 km

How big is Thetford Biomass Power Station?

Thetford Biomass Power Station has a recorded installed capacity of 38.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Thetford Biomass Power Station?

REPD records the operator as Energy Power Resources. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Thetford Biomass Power Station approved and built?

The application was submitted on 23 June 1994. Permission was granted on 5 May 1995, 10 months later. The site became operational on 2 October 1998, 41 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4.

Novarly Parcel · official public data, read properly · parcel.novarly.com