Thetford Biomass Power Station

Thetford Biomass Power Station is operational in Breckland with a recorded capacity of 38.5 MW, and has been generating since 1998-10-02.

38.5 MW
Capacity
as recorded in REPD
Operational
Status
since 1998-10-02
Biomass (dedicated)
Technology
Energy Power Resources
Breckland
Authority
England

Planning and build timeline

Application submitted1994-06-23
Permission granted1995-05-05
10 months after submission
Operational1998-10-02
41 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Non Agricultural agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Raf Honington Solar Farm
Solar Photovoltaics · Under Construction
11.2 km
Honington Solar Farm
Solar Photovoltaics · Operational
13.612.9 km
Ingham North Solar
Solar Photovoltaics · Operational
14.214.5 km
Hall Farm, West End Northwold - Solar Farm
Solar Photovoltaics · Operational
1014.8 km
Hall Farm, West End Northwold - Solar Farm
Battery · Operational
7.514.8 km
HMP Wayland - Solar Panels
Solar Photovoltaics · Operational
0.3414.9 km
Toggam Farm - Anaerobic Digestion Plant
Anaerobic Digestion · Operational
114.9 km

How big is Thetford Biomass Power Station?

Thetford Biomass Power Station has a recorded installed capacity of 38.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Thetford Biomass Power Station?

REPD records the operator as Energy Power Resources. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Thetford Biomass Power Station approved and built?

The application was submitted on 1994-06-23. Permission was granted on 1995-05-05, 10 months later. The site became operational on 1998-10-02, 41 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4.