Renewable sites › Lackford Estate Solar Park
Lackford Estate Solar Park
Lackford Estate Solar Park is operational in West Suffolk with a recorded capacity of 20.9 MW, and has been generating since 2014-03-31.
Planning and build timeline
| Application submitted | 2013-08-13 |
| Permission granted | 2013-11-02 3 months after submission |
| Operational | 2014-03-31 5 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 4 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
West Suffolk’s record on solar
West Suffolk has decided 29 solar farms and approved 97%, taking a median of 2.9 months. See every solar farm decision in West Suffolk →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Lackford Landfill Scheme Landfill Gas · Operational | 1.2 | 1.9 km |
Symonds Farm Power Ltd (Farm AD) Anaerobic Digestion · Operational | 1.4 | 3.9 km |
West Suffolk College, Out Risbygate Street - Solar Panels Solar Photovoltaics · Under Construction | 0.55 | 7.5 km |
Ingham North Solar Solar Photovoltaics · Operational | 14.2 | 7.6 km |
Bay Farm Solar Photovoltaics · Operational | 8.1 | 8.2 km |
British Sugar - Bury Anaerobic Digestion · Operational | 5 | 8.8 km |
Easlea Road - Solar Photovoltaic Panels Solar Photovoltaics · Operational | 0.62 | 10.6 km |
Honington Solar Farm Solar Photovoltaics · Operational | 13.6 | 13.4 km |
How big is Lackford Estate Solar Park?
Lackford Estate Solar Park has a recorded installed capacity of 20.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Lackford Estate Solar Park?
REPD records the operator as Lackford Estate Solar Park Ltd. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Lackford Estate Solar Park approved and built?
The application was submitted on 2013-08-13. Permission was granted on 2013-11-02, 3 months later. The site became operational on 2014-03-31, 5 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1338.