Novarly ParcelRenewable sites

Renewable sitesBritish Sugar - Bury

British Sugar - Bury

British Sugar - Bury is operational in West Suffolk with a recorded capacity of 5 MW, and has been generating since 2016-09-15.

5 MW
Capacity
as recorded in REPD
Operational
Status
since 2016-09-15
Anaerobic Digestion
Technology
British Sugar
West Suffolk
Authority
England

Planning and build timeline

Application submitted2014-10-09
Permission granted2014-12-11
2 months after submission
Operational2016-09-15
21 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Urban agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
West Suffolk College, Out Risbygate Street - Solar Panels
Solar Photovoltaics · Under Construction
0.552 km
Easlea Road - Solar Photovoltaic Panels
Solar Photovoltaics · Operational
0.622 km
Symonds Farm Power Ltd (Farm AD)
Anaerobic Digestion · Operational
1.46.1 km
Ingham North Solar
Solar Photovoltaics · Operational
14.27.3 km
Lackford Landfill Scheme
Landfill Gas · Operational
1.27.4 km
Lackford Estate Solar Park
Solar Photovoltaics · Operational
20.98.8 km
Honington Solar Farm
Solar Photovoltaics · Operational
13.610.4 km
Raf Honington Solar Farm
Solar Photovoltaics · Under Construction
12.5 km

How big is British Sugar - Bury?

British Sugar - Bury has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates British Sugar - Bury?

REPD records the operator as British Sugar. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was British Sugar - Bury approved and built?

The application was submitted on 2014-10-09. Permission was granted on 2014-12-11, 2 months later. The site became operational on 2016-09-15, 21 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4877.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council