Novarly ParcelRenewable sites

Renewable sitesIngham North Solar

Ingham North Solar

Ingham North Solar is operational in West Suffolk with a recorded capacity of 14.2 MW, and has been generating since 2021-03-23.

14.2 MW
Capacity
as recorded in REPD
Operational
Status
since 2021-03-23
Solar Photovoltaics
Technology
Solafields/Ingham Renewables
West Suffolk
Authority
England

Planning and build timeline

Application submitted2016-09-26
Permission granted2017-03-24
6 months after submission
Operational2021-03-23
48 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 4 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

West Suffolk’s record on solar

West Suffolk has decided 29 solar farms and approved 97%, taking a median of 2.9 months. See every solar farm decision in West Suffolk

Other built sites within 15 km

SiteMWDistance
Honington Solar Farm
Solar Photovoltaics · Operational
13.65.8 km
Lackford Landfill Scheme
Landfill Gas · Operational
1.25.8 km
British Sugar - Bury
Anaerobic Digestion · Operational
57.3 km
Raf Honington Solar Farm
Solar Photovoltaics · Under Construction
7.4 km
Lackford Estate Solar Park
Solar Photovoltaics · Operational
20.97.6 km
West Suffolk College, Out Risbygate Street - Solar Panels
Solar Photovoltaics · Under Construction
0.557.8 km
Symonds Farm Power Ltd (Farm AD)
Anaerobic Digestion · Operational
1.48.5 km
Easlea Road - Solar Photovoltaic Panels
Solar Photovoltaics · Operational
0.629.1 km

How big is Ingham North Solar?

Ingham North Solar has a recorded installed capacity of 14.2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Ingham North Solar?

REPD records the operator as Solafields/Ingham Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Ingham North Solar approved and built?

The application was submitted on 2016-09-26. Permission was granted on 2017-03-24, 6 months later. The site became operational on 2021-03-23, 48 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6248.

Novarly Parcel · official public data, read properly · parcel.novarly.com