Green Croft Solar Farm

Green Croft Solar Farm is operational in County Durham with a recorded capacity of 5 MW, and has been generating since 2016-12-07.

5 MW
Capacity
as recorded in REPD
Operational
Status
since 2016-12-07
Solar Photovoltaics
Technology
Anesco
County Durham
Authority
England

Planning and build timeline

Application submitted2015-07-23
Permission granted2015-11-04
3 months after submission
Operational2016-12-07
13 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 4 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

County Durham’s record on solar

County Durham has decided 46 solar farms and approved 93%, taking a median of 2 months. See every solar farm decision in County Durham

Other built sites within 15 km

SiteMWDistance
Chapman's Well
Landfill Gas · Operational
10.6 km
Greencroft Estate Turbines
Wind Onshore · Operational
40.8 km
Holmside Hall
Wind Onshore · Operational
2.83.8 km
Langley Moor
Wind Onshore · Operational
84.7 km
Land Adjacent to Thomas Swan and Co Ltd.
Anaerobic Digestion · Operational
15.1 km
Hownsgill Industrial Park
Solar Photovoltaics · Under Construction
56.8 km
Derwentside Environmental Testing Servs Limited - Solar pv panels
Solar Photovoltaics · Operational
0.387 km
High Hedley Hope 2 (Extension)
Wind Onshore · Operational
5.29.4 km

How big is Green Croft Solar Farm?

Green Croft Solar Farm has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Green Croft Solar Farm?

REPD records the operator as Anesco. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Green Croft Solar Farm approved and built?

The application was submitted on 2015-07-23. Permission was granted on 2015-11-04, 3 months later. The site became operational on 2016-12-07, 13 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5380.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council