Renewable sitesGreen Croft Solar Farm

Green Croft Solar Farm

Green Croft Solar Farm is an operational 5 MW solar farm in County Durham, generating since 7 December 2016. Planning permission was granted on 4 November 2015, 3 months after submission. Operator of record: Anesco.

5 MW
Capacity
as recorded in REPD
Operational
Status
since 7 December 2016
Solar Photovoltaics
Technology
Anesco
County Durham
Authority
England

Planning and build timeline

Application submitted23 July 2015
Permission granted4 November 2015
3 months after submission
Operational7 December 2016
13 months after consent

Screening a site of your own?

RedlineUK · £39

County Durham approves 93% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Green Croft Solar Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 4 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

County Durham’s record on solar

County Durham has decided 46 solar farms and approved 93%, taking a median of 2 months. See every solar farm decision in County Durham

Other built sites within 15 km

SiteMWDistance
Landfill Gas · Operational
10.6 km
Wind Onshore · Operational
40.8 km
Wind Onshore · Operational
2.83.8 km
Wind Onshore · Operational
84.7 km
Anaerobic Digestion · Operational
15.1 km
Solar Photovoltaics · Under Construction
56.8 km
Solar Photovoltaics · Operational
0.387 km
Wind Onshore · Operational
2.49.4 km

How big is Green Croft Solar Farm?

Green Croft Solar Farm has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Green Croft Solar Farm?

REPD records the operator as Anesco. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Green Croft Solar Farm approved and built?

The application was submitted on 23 July 2015. Permission was granted on 4 November 2015, 3 months later. The site became operational on 7 December 2016, 13 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5380.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode