Renewable planning › Onshore wind › Aberdeenshire
Onshore wind planning in Aberdeenshire
Aberdeenshire has decided 118 onshore wind schemes and approved 69% of them, taking a median of 12.7 months to decide. Consented capacity: 490 MW. 40 applications still awaiting a decision.
How Aberdeenshire compares
Against the 75 UK authorities with 5+ onshore wind decisions, Aberdeenshire sits in the 51st percentile for approval rate (1 points above the England average) and the 58th percentile for speed.
Decisions by year
Onshore wind decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.
Every recorded scheme (176)
| Scheme | MW | Status | Decided |
|---|---|---|---|
Auchorie Farm, Midmar - Wind Turbines Private Developer · APP/2026/0348 | 1.6 | Application Submitted | 2026-03-05 |
Mains Of Cairnbrogie, Oldmeldrum - Wind turbine Mountwest 838 Limited · APP/2025/2052 | 4.2 | Application Submitted | 2026-01-08 |
Ferniebrae Barras - Wind turbine CWE V27 Limited · APP/2024/2094 · 12.2 mo to decide | 0.3 | Awaiting Construction | 2025-12-24 |
Fadlydyke, Maud - Wind Turbine Green Cat Renewables · APP/2025/1950 | 1 | Application Submitted | 2025-12-12 |
Lan At Hilton, Park Farm - Wind Turbine Private Developer · APP/2025/1895 | 0.23 | Application Submitted | 2025-12-01 |
Mains Of Cairnbrogie, Oldmeldrum - Wind turbine Mountwest 838 Limited · APP/2024/0230 | 4.2 | Revised | 2025-10-24 |
Auchorie Farm, Midmar - Wind Turbines Private Developer · APP/2023/1651 | 1.7 | Revised | 2025-10-01 |
Logierieve Farm, Udny - Wind Turbine Roderic Bruce · APP/2025/1379 | 1 | Application Submitted | 2025-09-30 |
Balmacassie Brae, Balmacassie Commercial Park - Wind Power Tower Film Ocean Limited · APP/2024/1248 | 0.1 | Application Withdrawn | 2025-08-27 |
Logierieve Farm, Udny - Wind Turbine Roderic Bruce · APP/2024/1187 | 0.25 | Revised | 2025-05-07 |
Hill of Stoneyfield - Wind Turbines Wind 2 Limited · APP/2025/0514 | 14.4 | Application Submitted | 2025-05-06 |
Little Elrick, Maud - Wind Turbine Constantine Group Limited · APP/2024/1835 · 4.9 mo to decide | 0.23 | Awaiting Construction | 2025-04-17 |
Rivestone, Kinnoir - Wind Turbine CWE V27 Limited · APP/2024/2090 · 3.7 mo to decide | 0.3 | Awaiting Construction | 2025-04-09 |
Greenside Extension - Wind Turbines Greenside Wind Energy Limited · APP/2024/0229 · 12.7 mo to decide | 7.05 | Awaiting Construction | 2025-03-27 |
Cornabo, Monymusk - Wind turbines Clarke · APP/2024/0631 · 9.4 mo to decide | 3.9 | Awaiting Construction | 2025-01-29 |
Rivestone, Kinnoir - Wind Turbine CWE V27 Limited · APP/2023/2219 · 11.7 mo to decide | 0.3 | Revised | 2024-11-20 |
Logierieve Farm, Udny - Wind Turbine Roderic Bruce · APP/2024/1516 | — | Application Submitted | 2024-10-11 |
Upper Dagie, Torphins - Wind turbines Constantine Group Limited · APP/2024/0723 · 5 mo to decide | 0.85 | Awaiting Construction | 2024-10-03 |
Jacobshall, Gamrie - Wind Turbine CWE Jacobshell Limited · APP/2023/2005 · 10.1 mo to decide | 0.33 | Awaiting Construction | 2024-09-02 |
Ferniebrae Barras - Wind turbine CWE V27 Limited · APP/2023/2235 · 8.4 mo to decide | 0.3 | Revised | 2024-08-16 |
St Johns Wells, Fyvie - Wind Turbine St Johns Wells Wind Farm Limited · APP/2024/1102 | 0.8 | Application Submitted | 2024-07-04 |
Wagglehill, Cuminestown - Wind Turbine Harpers Transport · APP/2024/0508 · 1.3 mo to decide | 0.22 | Application Refused | 2024-06-06 |
HydroGlen Project - Glensaugh Farm The James Hutton Institute · APP/2023/2334 · 2.5 mo to decide | 1 | Under Construction | 2024-04-24 |
Cairndailly Farm - Wind turbine DC Smith Skelmonae Wind Farm Limited / Formartine Partnership / JKR Contractors Ltd · APP/2023/2303 | 3 | Application Submitted | 2024-01-11 |
Cairnbrogie Farm, Oldmeldrum - Wind Farm MountWest 838 Limited · APP/2022/2505 · 12 mo to decide | 3.6 | Awaiting Construction | 2023-12-13 |
Upper Mains Farm - Wind Turbine CWE V27 Limited · APP/2023/1968 | 0.45 | Application Submitted | 2023-11-01 |
Meikleton of Ardonald CleanEarth · APP/2023/1228 · 3.2 mo to decide | 1 | Awaiting Construction | 2023-10-04 |
Little Byth Wind Turbines, New Byth - Wind Turbine 4L Energy Limited · APP/2022/2255 · 8.6 mo to decide | 1 | Awaiting Construction | 2023-07-14 |
Edzell Airbase Wind Turbine Carnegie Base Services · APP/2023/0426 | 0.66 | Application Submitted | 2023-03-30 |
Netherton, Fisherford - Wind Turbine Speeca Energy Limited · APP/2023/0490 | — | Application Submitted | 2023-03-22 |
Craigneil Hill ESB Asset Development UK · APP/2018/0993 · 53 mo to decide | 35 | Awaiting Construction | 2022-09-29 |
St Fergus Renewable Energy Park Ednie Farms · APP/2019/2653 · 19.6 mo to decide | 3 | Under Construction | 2021-07-21 |
Skelmonae Wind Farm Extension Cardinghill Renewables · APP/2020/1024 | 1.6 | Application Submitted | 2020-06-26 |
Meikleton of Ardonald CleanEarth · APP/2019/0351 · 15.4 mo to decide | 1 | Revised | 2020-05-29 |
Netherton Private Developer · APP/2020/0293 | 0.9 | Revised | 2020-03-02 |
Cairnandrew Inicio Fresco · APP/2019/2280 · 1.1 mo to decide | 6 | Application Refused | 2019-12-02 |
Cairnbrogie Farm - Wind Turbine Mountwest 838 Limited · APP/2019/2559 | 1 | Revised | 2019-11-15 |
Deuchries Windfarm (extension) (Bradley 2) Blackfinch Energy · APP/2019/0017 · 7.4 mo to decide | 4.7 | Operational | 2019-08-30 |
Cardinghill Wind Turbine Cardinghill Renewables · APP/2017/2857 · 19.5 mo to decide | 1.5 | Revised | 2019-07-09 |
Mains of Cairnbrogie Private Developer · APP/2008/4093 · 102.6 mo to decide | 9.2 | Appeal Refused | 2017-06-23 |
North Haddo Green Cat Renewables · APP/2017/0869 | 1.6 | Planning Permission Expired | 2017-04-03 |
Mains of Cairnbrogie 2 Private Developer · APP/2010/0305 · 83.5 mo to decide | 6.9 | Revised | 2017-01-20 |
Brackenhills Farm J and LC Beattie Ltd · APP/2015/3800 · 11.7 mo to decide | 2.3 | Planning Permission Expired | 2016-12-06 |
Mountwest Wind Cluster (resubmission) Mountwest 838 · APP/2015/2965 · 11.1 mo to decide | 2.4 | Revised | 2016-08-24 |
Pressendye West Coast Energy · APP/2008/0237 · 101.2 mo to decide | 16.1 | Appeal Refused | 2016-07-12 |
Cairnandrew Wind Farm 1 Stop Renewables/King Edward Community Services · APP/2016/1848 · 0 mo to decide | 1.5 | Revised | 2016-06-28 |
Logie Newton Wind Farm Muirden Energy · APP/2015/2658 · 6.4 mo to decide | 1.6 | Appeal Refused | 2016-03-09 |
Land to the north west of Hill of Petty Green Cat Renewables · APP/2015/0112 · 12.7 mo to decide | 3.6 | Awaiting Construction | 2016-02-18 |
Glens of Foudland Wind Farm (Extension) GLID Wind Farms · APP/2015/2391 | 14 | Application Withdrawn | 2016-02-17 |
Land South West Of Backfield Farm 1 Stop Renewables · APP/2015/2092 · 4 mo to decide | 2.3 | Application Refused | 2015-10-29 |
Hill of Carlincraig wind turbines Newton Of Fortrie LLP/Muirden Energy · APP/2013/0987 · 27 mo to decide | 4.6 | Planning Permission Expired | 2015-07-02 |
Brackenhills Farm J & L C Beattie Ltd · APP/2014/2817 · 10.8 mo to decide | 2.3 | Revised | 2015-07-02 |
Cairnandrew Inicio-Fresco · APP/2014/1974 · 13.1 mo to decide | 1.5 | Revised | 2015-06-30 |
Woodlands Farm - Elion Scotfarms Ltd · APP/2008/4051 · 78.8 mo to decide | 2.3 | Appeal Refused | 2015-06-29 |
Greenleys Private Developer · APP/2014/2088 | 1.7 | Application Withdrawn | 2015-06-08 |
Backfield Farm Private Developer · APP/2014/2433 | 2.3 | Revised | 2015-06-04 |
Easter Tolmauds Frank A Smart & Son Ltd · APP/2014/1890 · 12.3 mo to decide | 1.6 | Operational | 2015-05-29 |
Hillhead of Turnerhall Formartine · APP/2013/1562 · 23 mo to decide | 3 | Application Refused | 2015-05-28 |
Hill Of Rothmaise wpd Rothmaise · APP/2014/2740 · 10 mo to decide | 4.6 | Appeal Refused | 2015-05-26 |
Floors Farm Wind Turbines artine Partnership Ltd · APP/2012/3956 · 29.8 mo to decide | 6.9 | Application Refused | 2015-05-26 |
Herscha Wind energy Project (Extension) Orkney Sustainable Energy · APP/2013/0587 · 26.5 mo to decide | 1.6 | Planning Permission Expired | 2015-05-20 |
Stony Hill Stony Hill Wind Farm Ltd · APP/2013/2064 | 18 | Application Withdrawn | 2015-05-19 |
Brucklaywaird Wind Farm Blue Energy (Auquhirie Extension) Limited · APP/2014/0254 · 14.6 mo to decide | 6.9 | Application Refused | 2015-04-30 |
Fraserburgh Harbour Wind Turbines Fraserburgh Harbour Commissioners · APP/2012/1101 | 1.8 | Application Withdrawn | 2015-04-29 |
Hill of Tillymorgan extension Unknown · APP/2014/2329 · 10 mo to decide | 2.3 | Appeal Refused | 2015-04-27 |
Cornabo Private Developer · APP/2014/1338 · 11.4 mo to decide | 2.7 | Planning Permission Expired | 2015-03-23 |
Gawnsmoss Cluster Farm Energy Consulting · APP/2012/2406 · 29 mo to decide | 2.4 | Operational | 2015-03-11 |
East Redhill Farms ClearWinds · APP/2014/4259 | 1.5 | Application Withdrawn | 2015-01-05 |
Auchmacoy Estate Wind Cluster Auchmacoy Estate · APP/2011/3710 | 2.4 | Application Withdrawn | 2014-11-11 |
Mormond Hill Windfarm Muirden Energy · APP/2011/3223 · 36 mo to decide | 27.6 | Appeal Refused | 2014-11-07 |
Ardlawhill Wood Wind Turbines Ventus Renewables Ltd · APP/2013/2188 · 15.7 mo to decide | 1 | Application Refused | 2014-11-06 |
Mains Of Collithie Muirden Energy · APP/2014/1032 · 5.7 mo to decide | 2.4 | Application Refused | 2014-08-25 |
Cairnborrow Engie (GDF Suez) · APP/2013/3282 · 10.5 mo to decide | 10 | Operational | 2014-08-25 |
Brotherton (formerly Paul Matthew Hill wind turbines) Renewable Energy Ventures · APP/2013/1156 · 15.3 mo to decide | 4.6 | Operational | 2014-07-15 |
Lodge Hill Vento Ludens · APP/2012/1971 · 23.8 mo to decide | 6.9 | Application Refused | 2014-06-06 |
Redhill Farms Clearwinds · APP/2013/3856 · 5.3 mo to decide | 6 | Application Refused | 2014-05-19 |
Burnside Wind Cluster Renewable Energy Ventures · APP/2013/2279 · 9.7 mo to decide | 4.6 | Application Refused | 2014-05-16 |
Hassiewells Hassiewells Renewables · APP/2013/0157 · 15.5 mo to decide | 6.9 | Appeal Refused | 2014-05-07 |
Deuchries Force 9 Energy / Catamount Energy/ Green Cat · APP/2012/3229 · 17.1 mo to decide | 6.9 | Operational | 2014-04-17 |
Meikleton Wind Farm Burcote Wind · APP/2012/3280 · 17.9 mo to decide | 12 | Revised | 2014-04-02 |
Hillhead of Bonnykelly Private Developer · APP/2013/3204 · 4.1 mo to decide | 2.3 | Application Refused | 2014-02-27 |
Tibberchindy Wind Farm Ventient (formerly Infinis) · APP/2012/3405 · 15.7 mo to decide | 18 | Application Refused | 2014-02-04 |
Holm and Hollymill Wind Turbines Good Energy Generation · APP/2012/0151 · 24.4 mo to decide | 4.6 | Application Refused | 2014-01-31 |
Hill of Corskie Gartly Wind Partnership · APP/2013/3216 · 2.8 mo to decide | 4.5 | Application Refused | 2014-01-06 |
Hill of Fishrie Novera Energy · APP/2011/2249 · 28.6 mo to decide | 11.3 | Application Refused | 2013-11-29 |
Boy's Hill Wind Cluster Private Developer · APP/2012/4218 · 9.3 mo to decide | 6.9 | Application Refused | 2013-10-21 |
Hill of Corksie Gartly Wind Partnership · APP/2013/2063 | 7.2 | Revised | 2013-10-08 |
Moss Side Farm Moss Side Farm Ltd · APP/2013/2454 · 2.1 mo to decide | 1 | Application Refused | 2013-10-01 |
BROWNIELEYS - 3 WIND TURBINES Brownieleys Renewables/Muirden Energy · APP/2012/1121 · 17.6 mo to decide | 7.5 | Operational | 2013-10-01 |
Hill of Braco PNE Wind UK Ltd (Brookfield) · APP/2013/0505 | 20 | Application Withdrawn | 2013-08-27 |
Hill of Tillymorgan Private Developer · APP/2008/0147 | 6 | Revised | 2013-05-15 |
Hill of Tillymorgan (Kirkton Farm) Wind turbines LocoGen/ Green Cat Renewables · APP/2011/0855 · 25.5 mo to decide | 9.6 | Operational | 2013-04-30 |
Jacksbank Wind Farm (Glenbervie) East Coast Viners · APP/2010/0487 · 38.1 mo to decide | 6.8 | Operational | 2013-04-26 |
Droop Hill Wind Farm x Macphie Of Glenbervie Ltd · APP/2009/1484 · 46.9 mo to decide | 4.6 | Operational | 2013-04-24 |
Ardlawhill Wood Wind Turbines Ventus Renewables Ltd · APP/2012/3495 | 1.4 | Revised | 2013-04-17 |
Bogmuir Farm Wind Turbine DM Cargill Ltd · APP/2012/3323 | 1 | Application Withdrawn | 2013-04-02 |
Droop Hill Wind Farm Macphie Of Glenbervie Ltd · APP/2006/3278 | 3.9 | Application Withdrawn | 2013-03-25 |
Coldhome Wind Turbines Private Developer · APP/2012/3367 | 1.5 | Application Withdrawn | 2013-01-22 |
Hill of Skilmafilly Cloffrickford (Denmore) Wind Farm SAC Environment And Design · APP/2011/0692 · 22.5 mo to decide | 6.9 | Operational | 2013-01-18 |
Hill of Easterton Extension 2 Mackies Limited · APP/2011/2120 · 18.3 mo to decide | 2.3 | Application Refused | 2012-12-24 |
Kempstone Hill Wind Turbines Kempstone Hill Wind Energy · APP/2012/2595 | 2.4 | Application Withdrawn | 2012-12-21 |
Easter Melrose Wind Energy Project Melrose Farms · APP/2011/2473 · 15.9 mo to decide | 1.5 | Operational | 2012-11-28 |
Auchinderran Wind Farm Green Cat Renewables · APP/2010/3417 · 23.9 mo to decide | 2.4 | Operational | 2012-11-08 |
Backhill of Yonderton Wind Cluster Private Developer · APP/2010/3054 · 23.8 mo to decide | 4.6 | Operational | 2012-11-02 |
Milton of Fisherie Wind Cluster LocoGen · APP/2011/1659 · 17.3 mo to decide | 4.6 | Operational | 2012-11-02 |
Shielburn Farm Green Cat Renewables · APP/2009/4072 · 34.2 mo to decide | 6.9 | Operational | 2012-10-24 |
Upper Wheedlemont Farm J & A�Wilson Ltd · APP/2009/3583 · 35 mo to decide | 1.7 | Operational | 2012-10-04 |
Easter Tulloch Wind Farm (Tullo Extension) N R Gammie Partnership · APP/2011/2603 · 13.4 mo to decide | 25 | Operational | 2012-09-21 |
Burnside Wind Cluster Pennant Wind Energy Ventures · APP/2012/1695 · 2.9 mo to decide | 6.9 | Revised | 2012-09-13 |
Tullo Wind Farm South (Ext.) Eneco · APP/2011/3694 · 9.5 mo to decide | 10 | Operational | 2012-09-13 |
Cairnborrow WCE · APP/2011/1639 · 15 mo to decide | 25 | Revised | 2012-08-31 |
Yonderton Farm J & G Energy Ltd · APP/2011/3206 · 11.4 mo to decide | 1 | Application Refused | 2012-08-31 |
Castle of Auchry Farm Green Cat Renewables · APP/2010/0067 · 31 mo to decide | 2.4 | Operational | 2012-08-14 |
Hillhead of Bonnykelly GEM Electric · APP/2010/4039 · 18.2 mo to decide | 4.6 | Revised | 2012-06-28 |
St Johns Wells Wind Cluster Extension Green Cat Renewables · APP/2009/4121 · 29.3 mo to decide | 3.2 | Operational | 2012-06-22 |
Yowlie Wind Cluster Yowlie Energy Ltd · APP/2011/4273 · 3.7 mo to decide | 3.2 | Application Refused | 2012-05-01 |
Upper Kinknockie Wind Farm Private Developer · APP/2011/3763 | 1.5 | Application Withdrawn | 2012-04-18 |
Cairnbrogie Wind Farm Green Cat Renewables · APP/2011/1917 · 8.9 mo to decide | 4.6 | Application Refused | 2012-03-05 |
Tullo Wind Farm North Extension (Shiels Wind Farm) Eneco · APP/2011/2389 · 7.1 mo to decide | 7.5 | Operational | 2012-02-29 |
St Fergus Moss Wind Farm Greenspan Electric St Fergus Ltd · APP/2010/2118 · 19.9 mo to decide | 6 | Operational | 2012-02-23 |
Burnside Wind Cluster Pennant Wind Energy Ventures · APP/2011/3185 | 6.9 | Revised | 2012-01-23 |
Cairnmore Extension Greenspan Electric Cairnmore Ltd · APP/2011/0545 · 10.4 mo to decide | 4.3 | Application Refused | 2012-01-05 |
Hill of Corskie Oosterhof & Co · APP/2008/2833 · 37 mo to decide | 8 | Revised | 2011-09-29 |
Land at Overside and Greenwellheads Farms Greenside Wind Energy Ltd · APP/2011/1024 · 5.5 mo to decide | 9.2 | Operational | 2011-09-13 |
Burnside Wind Cluster Renewable Energy Ventures · APP/2011/0174 | 6.9 | Revised | 2011-06-10 |
Cairncake Alan Twatt (Potatoes) Ltd · APP/2010/0755 · 14.8 mo to decide | 4.6 | Application Refused | 2011-06-09 |
West Knock Wind Cluster West Knock Farm · APP/2009/2439 · 20.8 mo to decide | 2.4 | Operational | 2011-04-21 |
Mornflake Oats Wind Turbine Mornflake Oats/ Hamlyns Oats · APP/2008/2874 · 32 mo to decide | 2.3 | Operational | 2011-04-06 |
Hillhead of Auquhirie Octopus Investements/Blue Energy (previously Auquhirie Land Company Ltd) · APP/2009/3567 · 14.2 mo to decide | 6.9 | Operational | 2011-01-10 |
Clashindarroch Vattenfall · APP/2009/1380 · 18.4 mo to decide | 37 | Operational | 2010-12-14 |
Burnside of Idoch Scottish and Southern Energy (SSE) · APP/2010/0405 · 9 mo to decide | 3.2 | Appeal Refused | 2010-11-12 |
Cairn Hill Private Developer · APP/2010/1147 · 7.1 mo to decide | 2.4 | Application Refused | 2010-11-12 |
Greenhill Croft Green Cat Renewables · APP/2009/3456 · 11.7 mo to decide | 4.6 | Operational | 2010-10-11 |
Auchenten Private Developer · APP/2009/3610 · 11.1 mo to decide | 2.4 | Appeal Refused | 2010-10-08 |
Muirake Vento Ludens · APP/2009/3565 · 10.2 mo to decide | 4.6 | Operational | 2010-09-08 |
Yonderton Farm Green Cat Renewables · APP/2010/1564 · 2.3 mo to decide | 1 | Operational | 2010-07-23 |
Cloffrickford Skelmonae Windfarm Ltd · APP/2009/1278 | 9.2 | Application Withdrawn | 2010-06-09 |
Meikle Carewe The Renewables Infrastructure Group (TRIG) · APP/2006/3934 · 41.7 mo to decide | 10 | Operational | 2010-05-20 |
Upper Ardgrain Wind Farm Green Cat Renewables · APP/2007/4747 · 29.2 mo to decide | 2.4 | Operational | 2010-04-27 |
Little Byth Lovie Ltd · APP/2009/1044 · 8.5 mo to decide | 4.5 | Operational | 2009-12-24 |
St John Hill Auquhirie Land Company Ltd · APP/2008/2570 · 17 mo to decide | 7.7 | Operational | 2009-12-10 |
Bogenlea Farm Eco2 · APP/2009/1541 · 6.7 mo to decide | 2.3 | Operational | 2009-12-10 |
Cairnmore Farm Private Developer · APP/2008/1486 · 18.3 mo to decide | 2.6 | Operational | 2009-10-27 |
Strath of Brydock - Extension Green Cat Renewables · APP/2008/2404 · 11 mo to decide | 2.3 | Operational | 2009-10-16 |
Boyndie Airfield Extension Boyndie Wind Farm · APP/2008/2761 · 12.3 mo to decide | 2.3 | Operational | 2009-08-14 |
Kildrummy Windfarm Greencoat UK Wind/Bay Wa .r.e/ SunGift · APP/2006/4911 · 31.6 mo to decide | 18.4 | Operational | 2009-08-06 |
Clochnahill Wind Farm Private Developer · 36.3 mo to decide | 5.2 | Operational | 2009-08-05 |
Gairnieston Farm Private Developer · APP/2007/3775 · 22.4 mo to decide | 2.3 | Operational | 2009-07-31 |
Cloffrickford Farm Private Developer · APP/2008/3667 | 10 | Application Withdrawn | 2009-07-07 |
Gordonstown Hill Wind Farm Ventient (formerly Infinis) · APP/2008/4244 · 6.2 mo to decide | 12.5 | Operational | 2009-07-02 |
Haddo Private Developer · APP/2006/3637 · 33.3 mo to decide | 4.6 | Operational | 2009-06-24 |
House O'Hill Green Cat Renewables · APP/2008/1722 · 12.7 mo to decide | 5 | Operational | 2009-06-05 |
Denhill Private Developer · APP/2006/3651 · 32.7 mo to decide | 2.3 | Operational | 2009-06-05 |
Skelmonae Wind Farm Private Developer · APP/2007/2823 · 19.7 mo to decide | 3.2 | Operational | 2009-02-24 |
Hillhead of Auquhirie Polar Energy · APP/2006/1777 | 6 | Revised | 2008-10-02 |
Hill of Balquhindachy extension Private Developer · APP/2007/1191 · 17.7 mo to decide | 1.7 | Operational | 2008-09-09 |
Hill of Fiddes Infinis, previously Broadview Energy · APP/2007/3578 · 6.9 mo to decide | 6.9 | Operational | 2008-04-01 |
North Red Bog Green Cat Renewables · APP/2007/2794 · 8 mo to decide | 1.6 | Operational | 2008-03-07 |
Strath of Brydock Green Cat Renewables · APP/2006/3227 · 17.9 mo to decide | 4.6 | Operational | 2008-02-25 |
St. Johns Hill K E Projects AF · 2004/4666 · 35.1 mo to decide | 7.65 | Operational | 2007-11-26 |
Mains of Hatton Eco2 /GreenCAT · APP/2006/4452 · 10.1 mo to decide | 2.4 | Operational | 2007-09-19 |
Hill of Easterton Extension Mackies · APP/2005/3308 · 21.6 mo to decide | 2 | Operational | 2007-07-18 |
Methlick Farmers Wind Energy Project Orkney Sustainable Energy · Various · 9 mo to decide | 12 | Operational | 2007-07-01 |
St John's Well Green Cat Renewables · APP/2006/3851 · 5.6 mo to decide | 2.4 | Operational | 2007-03-20 |
Clochnahill Windfarm Private Developer · ENQ/2005/0667 · 10.4 mo to decide | 6 | Application Refused | 2007-03-20 |
Courtstone Wind Turbine Private Developer · APP/2006/3646 · 0 mo to decide | 2.3 | Operational | 2006-09-15 |
Hill of Snowy Slack Npower Renewables · M/APP/2004/4603 | 22 | Application Withdrawn | 2006-05-09 |
Hill of Garvock Wind Energy Project Orkney Sustainable Energy · SO 30676PF | 15 | Application Withdrawn | 2005-10-18 |
Stoneyhill Ron Shanks Waste Management Ltd · N020466PF | 30.6 | Application Withdrawn | 2005-06-10 |
Hill of Garvock Wind Energy Project (2) Orkney Sustainable Energy · APP2004/1412 · 6.1 mo to decide | 15 | Application Refused | 2004-10-26 |
Boyndie Airfield RDC Scotland Ltd/ Falck Renewables · APP/2003/1692 · 13 mo to decide | 16.7 | Operational | 2004-07-23 |
Tullo Farm West Coast Energy (agents for Tullo Wind Ltd and GE Wind) · APP/2003/0756 · 8.6 mo to decide | 17.5 | Operational | 2004-06-30 |
Dummuie Tetro Energy Ltd (ECO2) · APP/2003/0084 · 6 mo to decide | 12.3 | Operational | 2004-02-20 |
Hill of Easterton Mackies | 2.5 | Operational | 2003-10-16 |
Meikle Carewe Renewable Energy Systems (RES) · S000295PF · 20.5 mo to decide | 14 | Revised | 2001-12-04 |
Glens of Foudland Green Investment Bank (Blackrock) · SO10069PF · 8.3 mo to decide | 26 | Operational | 2001-10-04 |
Does Aberdeenshire approve onshore wind schemes?
Yes — of the 118 onshore wind schemes Aberdeenshire has decided, 69% were approved (81 granted, 37 refused). The UK-wide rate for onshore wind is 68%.
How long does a onshore wind scheme application take in Aberdeenshire?
The median time from application to decision is 12.7 months, against a UK median of 11.5 months for onshore wind. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.
How much onshore wind capacity has Aberdeenshire consented?
490 MW has been consented across 81 approved schemes, with 214 MW refused. A further 40 applications awaits a decision.
Other technologies in Aberdeenshire
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.
Novarly Parcel · official public data, read properly · parcel.novarly.com
Screen a specific site here · All authorities · UK property report