Novarly ParcelRenewable sites

Renewable sitesHarbour Road

Harbour Road

Harbour Road is an operational 2.6 MW biomass plant in South Ayrshire, generating since 18 March 2017. Planning permission was granted on 5 July 2016, 1 months after submission. Operator of record: Glennon Brothers Troon.

2.6 MW
Capacity
as recorded in REPD
Operational
Status
since 18 March 2017
Biomass (dedicated)
Technology
Glennon Brothers Troon
South Ayrshire
Authority
Scotland

Planning and build timeline

Application submitted13 June 2016
Permission granted5 July 2016
1 months after submission
Operational18 March 2017
8 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in South Ayrshire: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Harbour Road’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Other built sites within 15 km

SiteMWDistance
Biomass (dedicated) · Operational
264.5 km
EfW Incineration · Under Construction
175.8 km
Solar Photovoltaics · Under Construction
56 km
Wind Onshore · Under Construction
36.2 km
Anaerobic Digestion · Operational
16.2 km
Wind Onshore · Operational
7.56.4 km
Solar Photovoltaics · Under Construction
19.96.4 km
Wind Onshore · Operational
2.56.5 km

How big is Harbour Road?

Harbour Road has a recorded installed capacity of 2.6 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Harbour Road?

REPD records the operator as Glennon Brothers Troon. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Harbour Road approved and built?

The application was submitted on 13 June 2016. Permission was granted on 5 July 2016, 1 months later. The site became operational on 18 March 2017, 8 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6138.

Novarly Parcel · official public data, read properly · parcel.novarly.com