FMC Technologies

FMC Technologies is operational in Fife with a recorded capacity of 1.5 MW, and has been generating since 2011-12-07.

1.5 MW
Capacity
as recorded in REPD
Operational
Status
since 2011-12-07
Wind Onshore
Technology
FMC Technologies
Fife
Authority
Scotland

Planning and build timeline

Application submitted2009-02-12
Permission granted2009-12-22
10 months after submission
Operational2011-12-07
23 months after consent

Fife’s record on onshore wind

Fife has decided 28 onshore wind schemes and approved 54%, taking a median of 16.1 months. See every onshore wind scheme decision in Fife

Other built sites within 15 km

SiteMWDistance
F M C Land, Pitreavie Business Park
Wind Onshore · Operational
1.50.3 km
Dunfermline EDI4
Solar Photovoltaics · Operational
1.93.6 km
Lochhead Landfill CHP
Anaerobic Digestion · Operational
1.74.7 km
St Margarets Bay
Solar Photovoltaics · Operational
0.24.7 km
Dunfermline North - Solar Photovoltaic Array/Battery storage
Battery · Under Construction
204.9 km
Dunfermline North - Solar Photovoltaic Array/Battery storage
Solar Photovoltaics · Under Construction
29.94.9 km
Lochhead
Landfill Gas · Operational
25 km
Goathill Quarry Turbine
Wind Onshore · Operational
28.5 km

How big is FMC Technologies?

FMC Technologies has a recorded installed capacity of 1.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates FMC Technologies?

REPD records the operator as FMC Technologies. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was FMC Technologies approved and built?

The application was submitted on 2009-02-12. Permission was granted on 2009-12-22, 10 months later. The site became operational on 2011-12-07, 23 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2687.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council