Renewable sites › FMC Technologies
FMC Technologies
FMC Technologies is operational in Fife with a recorded capacity of 1.5 MW, and has been generating since 2011-12-07.
Planning and build timeline
| Application submitted | 2009-02-12 |
| Permission granted | 2009-12-22 10 months after submission |
| Operational | 2011-12-07 23 months after consent |
Fife’s record on onshore wind
Fife has decided 28 onshore wind schemes and approved 54%, taking a median of 16.1 months. See every onshore wind scheme decision in Fife →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
F M C Land, Pitreavie Business Park Wind Onshore · Operational | 1.5 | 0.3 km |
Dunfermline EDI4 Solar Photovoltaics · Operational | 1.9 | 3.6 km |
Lochhead Landfill CHP Anaerobic Digestion · Operational | 1.7 | 4.7 km |
St Margarets Bay Solar Photovoltaics · Operational | 0.2 | 4.7 km |
Dunfermline North - Solar Photovoltaic Array/Battery storage Battery · Under Construction | 20 | 4.9 km |
Dunfermline North - Solar Photovoltaic Array/Battery storage Solar Photovoltaics · Under Construction | 29.9 | 4.9 km |
Lochhead Landfill Gas · Operational | 2 | 5 km |
Goathill Quarry Turbine Wind Onshore · Operational | 2 | 8.5 km |
How big is FMC Technologies?
FMC Technologies has a recorded installed capacity of 1.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates FMC Technologies?
REPD records the operator as FMC Technologies. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was FMC Technologies approved and built?
The application was submitted on 2009-02-12. Permission was granted on 2009-12-22, 10 months later. The site became operational on 2011-12-07, 23 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2687.