Renewable sites › Lochhead Landfill CHP
Lochhead Landfill CHP
Lochhead Landfill CHP is operational in Fife with a recorded capacity of 1.7 MW, and has been generating since 2014-03-31.
Planning and build timeline
| Application submitted | 2011-03-07 |
| Permission granted | 2011-08-18 5 months after submission |
| Operational | 2014-03-31 31 months after consent |
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Lochhead Landfill Gas · Operational | 2 | 0.3 km |
Dunfermline North - Solar Photovoltaic Array/Battery storage Solar Photovoltaics · Under Construction | 29.9 | 0.4 km |
Dunfermline North - Solar Photovoltaic Array/Battery storage Battery · Under Construction | 20 | 0.4 km |
FMC Technologies Wind Onshore · Operational | 1.5 | 4.7 km |
F M C Land, Pitreavie Business Park Wind Onshore · Operational | 1.5 | 5 km |
Dunfermline EDI4 Solar Photovoltaics · Operational | 1.9 | 6.1 km |
Goathill Quarry Turbine Wind Onshore · Operational | 2 | 9.4 km |
St Margarets Bay Solar Photovoltaics · Operational | 0.2 | 9.4 km |
How big is Lochhead Landfill CHP?
Lochhead Landfill CHP has a recorded installed capacity of 1.7 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Lochhead Landfill CHP?
REPD records the operator as Fife Council. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Lochhead Landfill CHP approved and built?
The application was submitted on 2011-03-07. Permission was granted on 2011-08-18, 5 months later. The site became operational on 2014-03-31, 31 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 269.