Renewable sitesFlint Landfill Site Castle Park

Flint Landfill Site Castle Park

Flint Landfill Site Castle Park is operational in Flintshire with a recorded capacity of 2 MW, and has been generating since 2021-02-01.

2 MW
Capacity
as recorded in REPD
Operational
Status
since 2021-02-01
Solar Photovoltaics
Technology
Flintshire County Council
Flintshire
Authority
Wales

Planning and build timeline

Application submitted2019-04-29
Permission granted2019-08-16
4 months after submission
Operational2021-02-01
18 months after consent

Flintshire’s record on solar

Flintshire has decided 11 solar farms and approved 82%, taking a median of 6.4 months. See every solar farm decision in Flintshire

Other built sites within 15 km

SiteMWDistance
Kingspan
Wind Onshore · Operational
1.85.6 km
Crumps Yard Solar Farm
Solar Photovoltaics · Operational
1.67 km
Parc Adfer EfW
EfW Incineration · Operational
167.3 km
Shotwick Solar Farm
Solar Photovoltaics · Operational
72.28 km
Aldi Distribution Centre - Neston
Solar Photovoltaics · Operational
1.28 km
Toyota Motor Manufacturing Uk - Deeside
Solar Photovoltaics · Operational
3.88.3 km
National Grid Electricity Substation, Capenhurst Lane - Battery Storage
Battery · Operational
10012.4 km
Capenhurst Lane, Capenhurst - Battery storage
Battery · Under Construction
5712.7 km

How big is Flint Landfill Site Castle Park?

Flint Landfill Site Castle Park has a recorded installed capacity of 2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Flint Landfill Site Castle Park?

REPD records the operator as Flintshire County Council. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Flint Landfill Site Castle Park approved and built?

The application was submitted on 2019-04-29. Permission was granted on 2019-08-16, 4 months later. The site became operational on 2021-02-01, 18 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 7400.